Welcome to ExamTopics
ExamTopics Logo
- Expert Verified, Online, Free.
exam questions

Exam PMP All Questions

View all questions & answers for the PMP exam

Exam PMP topic 1 question 1033 discussion

Actual exam question from PMI's PMP
Question #: 1033
Topic #: 1
[All PMP Questions]

A project that has to be delivered by the targeted date has been delayed due to an unforeseen risk occurrence. How should the project manager compress the project to ensure the completion date is not affected?

  • A. Add more project resources
  • B. Fast-track the project
  • C. Reduce the project scope
  • D. Increase the project cost
Show Suggested Answer Hide Answer
Suggested Answer: B 🗳️

Comments

Chosen Answer:
This is a voting comment (?) , you can switch to a simple comment.
Switch to a voting comment New
MonBouj
1 month ago
Selected Answer: B
B. Fast-track the project Fast-tracking allows the project manager to recover lost time by rearranging the project schedule without necessarily compromising on deliverables, as long as the project team can handle the increased risks associated with overlapping tasks.
upvoted 1 times
...
victory108
1 month ago
Selected Answer: B
B. Fast-track the project
upvoted 1 times
...
Abdelmonm
10 months, 3 weeks ago
Selected Answer: B
Fast-tracking involves reordering or overlapping project activities that would normally be done in sequence. This approach can help in speeding up the project schedule without necessarily increasing the project cost significantly.
upvoted 1 times
...
Community vote distribution
A (35%)
C (25%)
B (20%)
Other
Most Voted
A voting comment increases the vote count for the chosen answer by one.

Upvoting a comment with a selected answer will also increase the vote count towards that answer by one. So if you see a comment that you already agree with, you can upvote it instead of posting a new comment.

SaveCancel
Loading ...