Welcome to ExamTopics
ExamTopics Logo
- Expert Verified, Online, Free.
exam questions

Exam PMP All Questions

View all questions & answers for the PMP exam

Exam PMP topic 1 question 1022 discussion

Actual exam question from PMI's PMP
Question #: 1022
Topic #: 1
[All PMP Questions]

In a complex project with several subcontractors, one subcontractor reports a likely delay in the schedule. This could affect the other subcontractors and impact their ability to deliver on time.

What should the project manager do first?

  • A. Assess the schedule and update the risk register.
  • B. Report the delay to all other subcontractors.
  • C. Change the milestones and sequence of work.
  • D. Escalate to senior management and the stakeholders.
Show Suggested Answer Hide Answer
Suggested Answer: A 🗳️

Comments

Chosen Answer:
This is a voting comment (?) , you can switch to a simple comment.
Switch to a voting comment New
MonBouj
1 month, 1 week ago
Selected Answer: A
A. Assess the schedule and update the risk register. By assessing the schedule, the project manager can determine the extent of the delay's impact on the overall project timeline and other subcontractors. Updating the risk register will help document the potential risk and its implications, allowing for informed decision-making and communication with stakeholders moving forward.
upvoted 1 times
...
victory108
1 month, 1 week ago
Selected Answer: A
A. Assess the schedule and update the risk register
upvoted 1 times
...
Abdelmonm
10 months, 3 weeks ago
Selected Answer: A
Assessing the schedule and updating the risk register is the most immediate and practical step for the project manager. This involves evaluating the impact of the likely delay, identifying potential risks to the project timeline, and documenting these in the risk register. This assessment provides a foundation for informed decision-making and proactive risk management. Once the project manager has a clear understanding of the situation, they can then take appropriate actions, such as adjusting the schedule, communicating with subcontractors, and escalating the issue if necessary.
upvoted 1 times
...
Community vote distribution
A (35%)
C (25%)
B (20%)
Other
Most Voted
A voting comment increases the vote count for the chosen answer by one.

Upvoting a comment with a selected answer will also increase the vote count towards that answer by one. So if you see a comment that you already agree with, you can upvote it instead of posting a new comment.

SaveCancel
Loading ...