Exam PMP topic 1 question 975 discussion

Actual exam question from PMI's PMP
Question #: 975
Topic #: 1
[All PMP Questions]

Before a daily standup, a team member informed the project manager that they have accepted a job offer at another company. The team member explains that they plan to present their resignation to the functional manager.

What should the project manager do next?

  • A. Contact the product owner and review the current sprint backlog.
  • B. Communicate to the team members at the daily standup.
  • C. Alert the functional manager about possible delivery delays.
  • D. Contact the functional manager and develop a mitigation strategy.
Show Suggested Answer Hide Answer
Suggested Answer: D 🗳️

Comments

Chosen Answer:
This is a voting comment (?). It is better to Upvote an existing comment if you don't have anything to add.
Switch to a voting comment New
victory108
1 month ago
Selected Answer: D
D. Contact the functional manager and develop a mitigation strategy
upvoted 1 times
...
que1010
5 months, 3 weeks ago
Why not B? After communicating in team to analysis the impact, PM will contact functional manager and develop a mitigation strategy?
upvoted 1 times
...
517f9da
7 months, 2 weeks ago
Selected Answer: D
Some answers are just off their rockers. "A" has nothing to do with the matter at hand. it comes when scheduled with or without the resignation. Mitigation start. will define how the backlog will look like and handled once the time comes to meet with the owner. This should be D. Contact the functional manager and develop a mitigation strategy. Explanation is Collaborating with the functional manager to develop a mitigation strategy helps address the potential impact on the project and ensures a smooth transition.
upvoted 1 times
...
Trytrio
11 months ago
Selected Answer: D
For me its D
upvoted 2 times
...
Abdelmonm
11 months ago
Selected Answer: D
The project manager should choose option D to contact the functional manager and develop a mitigation strategy. This ensures timely communication about the team member's resignation and allows for collaborative planning to address potential project impacts, including task redistribution and knowledge transfer.
upvoted 1 times
...
UppersquareCapital
11 months, 2 weeks ago
Selected Answer: B
It's important to communicate such information to the team promptly, and the daily standup is a suitable forum for sharing updates and potential impacts on the project. By informing the team during the standup, the project manager can ensure that everyone is aware of the situation and can collectively discuss how to manage the workload and any potential risks. While options A, C, and D may be relevant, immediate communication with the team is crucial to maintaining transparency and allowing the team to adjust to the changes in personnel. After the team is informed, the project manager can then consider discussing with the functional manager and addressing any potential delivery delays or developing a mitigation strategy.
upvoted 1 times
...
janojano
11 months, 2 weeks ago
Selected Answer: D
It's definitely not B nor C. The functional manager does not care about delays, he is not the PM, and informing the Team in the daily standup is not a priority. However, answer D, working with the functional manager to mitigate this issue and get more resources makes sense to me.
upvoted 1 times
...
ced45c8
11 months, 3 weeks ago
A is not answer as print backlog is development team to take care not product owner. as question is talking about functional manager, means organization is functional so this is functional manager responsibility to consider alternative solution
upvoted 1 times
...
odylec
12 months ago
Selected Answer: A
A is the answer. After view of the backlog the PM can provide the project manager with a clearer picture of the immediate tasks, dependencies, and potential risks involved in the departing team member's role. After assessing the situation and identifying specific risks and tasks, the project manager can then communicate effectively with the functional manager (Option D). This communication can be more targeted, providing the functional manager with the necessary details to formulate a mitigation strategy that addresses the identified risks and ensures the smooth continuation of project activities.
upvoted 2 times
...
Community vote distribution
A (35%)
C (25%)
B (20%)
Other
Most Voted
A voting comment increases the vote count for the chosen answer by one.

Upvoting a comment with a selected answer will also increase the vote count towards that answer by one. So if you see a comment that you already agree with, you can upvote it instead of posting a new comment.

SaveCancel
Loading ...
exam
Someone Bought Contributor Access for:
SY0-701
London, 1 minute ago