Due to price inflation, an agile project manager has identified that the available project funding will not be enough to bring on an additional team member for the upcoming iterations as initially planned. The project budget and release deadlines are tight. The existing cross-functional team is experienced.
What is the first approach the project manager should take?
victory108
1 day, 5 hours ago517f9da
6 months, 1 week agoodylec
10 months, 3 weeks ago