A project team is transitioning to agile delivery. The team uses a Kanban board to track progress. In the daily meetings, the team members have been reporting good progress. However, the cards on the board are not progressing toward "done."
What should the project manager do?
victory108
3 months ago517f9da
9 months, 1 week agohoomz
12 months agoTrytrio
1 year agoKennyMuffins
1 year agojosephsafiran
1 year ago58e5964
1 year agoUppersquareCapital
1 year, 1 month agoAbdelmonm
1 year, 1 month agoAbdelmonm
1 year agoAbdelmonm
1 year agoodylec
1 year, 1 month ago