A project team is transitioning to agile delivery. The team uses a Kanban board to track progress. In the daily meetings, the team members have been reporting good progress. However, the cards on the board are not progressing toward "done."
What should the project manager do?
victory108
3 days, 13 hours ago517f9da
6 months, 1 week agohoomz
9 months agoTrytrio
9 months, 3 weeks agoKennyMuffins
9 months, 3 weeks agojosephsafiran
10 months ago58e5964
10 months agoUppersquareCapital
10 months, 1 week agoAbdelmonm
10 months, 2 weeks agoAbdelmonm
10 months agoAbdelmonm
10 months agoodylec
10 months, 4 weeks ago