Welcome to ExamTopics
ExamTopics Logo
- Expert Verified, Online, Free.
exam questions

Exam PMP All Questions

View all questions & answers for the PMP exam

Exam PMP topic 1 question 946 discussion

Actual exam question from PMI's PMP
Question #: 946
Topic #: 1
[All PMP Questions]

During a risk management meeting, most of the project team members use a computer to iterate the quantitative risk analysis model numerous times. There will be a cumulative probability distribution (S-curve) representing the probability of achieving any particular outcome.

Which method should the project manager use to assess and manage project risks?

  • A. Influence diagrams
  • B. Sensitivity analysis
  • C. Decision tree analysis
  • D. Monte Carlo analysis
Show Suggested Answer Hide Answer
Suggested Answer: D 🗳️

Comments

Chosen Answer:
This is a voting comment (?) , you can switch to a simple comment.
Switch to a voting comment New
victory108
4 days, 13 hours ago
Selected Answer: D
D. Monte Carlo analysis
upvoted 1 times
...
517f9da
6 months, 1 week ago
Selected Answer: D
D. Monte Carlo analysis Explanation: Monte Carlo analysis is a quantitative risk analysis technique that involves running a simulation (often using a computer) to model the possible outcomes of a project based on the variability of risk factors. The result is a cumulative probability distribution (S-curve) that shows the probability of achieving different outcomes, helping the project manager assess and manage project risks effectively.
upvoted 1 times
...
Abdelmonm
10 months, 2 weeks ago
Selected Answer: D
Monte Carlo analysis is a quantitative risk analysis technique that uses computer simulations to model the likelihood of different outcomes in a project. It is particularly effective for assessing and managing project risks by considering the impact of uncertainty and variability. This technique helps in generating a cumulative probability distribution (S-curve) and provides a more realistic understanding of project outcomes.
upvoted 1 times
...
odylec
10 months, 3 weeks ago
Selected Answer: D
D is the answer. In the context of a risk management meeting where the project team members are extensively utilizing computers to iterate the quantitative risk analysis model, the most suitable method for assessing and managing project risks is Monte Carlo analysis (Option D). Monte Carlo analysis is a sophisticated quantitative risk analysis tool that involves running numerous simulations to evaluate the impact of various risks and uncertainties on project objectives. Its iterative nature aligns well with the described scenario of multiple iterations of the risk analysis model. Furthermore, Monte Carlo analysis produces cumulative probability distributions, such as S-curves, which offer a comprehensive representation of the likelihood of different project outcomes based on input variables and associated uncertainties.
upvoted 1 times
...
Community vote distribution
A (35%)
C (25%)
B (20%)
Other
Most Voted
A voting comment increases the vote count for the chosen answer by one.

Upvoting a comment with a selected answer will also increase the vote count towards that answer by one. So if you see a comment that you already agree with, you can upvote it instead of posting a new comment.

SaveCancel
Loading ...