A project manager is executing a large project with many stakeholders. One of the primary stakeholders is requesting a change to the project scope. The project manager knows that this scope change will not require much effort from the project team. The project manager is worried that going through the full change control process will hold up the project schedule.
What should the project manager do?
Kim222
2 weeks, 5 days ago517f9da
4 months, 1 week agoAbdelmonm
8 months, 2 weeks agopsvexam
8 months, 4 weeks ago