Welcome to ExamTopics
ExamTopics Logo
- Expert Verified, Online, Free.
exam questions

Exam PMP All Questions

View all questions & answers for the PMP exam

Exam PMP topic 1 question 904 discussion

Actual exam question from PMI's PMP
Question #: 904
Topic #: 1
[All PMP Questions]

A project manager is executing a large project with many stakeholders. One of the primary stakeholders is requesting a change to the project scope. The project manager knows that this scope change will not require much effort from the project team. The project manager is worried that going through the full change control process will hold up the project schedule.

What should the project manager do?

  • A. Ask the primary stakeholder for their official approval to avoid the change control process.
  • B. Implement the change in order to avoid changes to the schedule baseline.
  • C. Reject the change request because the project is already being executed.
  • D. Submit a formal change request since the change is affecting the project baseline.
Show Suggested Answer Hide Answer
Suggested Answer: D 🗳️

Comments

Chosen Answer:
This is a voting comment (?) , you can switch to a simple comment.
Switch to a voting comment New
Kim222
2 weeks, 5 days ago
Selected Answer: D
Handle work so that it flows according to schedule.
upvoted 1 times
...
517f9da
4 months, 1 week ago
Selected Answer: D
D. Submit a formal change request since the change is affecting the project baseline. Explanation: Even if the change does not require much effort, it is essential to follow the formal change control process to ensure that all changes are documented, reviewed, and approved, preventing potential issues and maintaining project integrity.
upvoted 1 times
...
Abdelmonm
8 months, 2 weeks ago
Selected Answer: D
Even if the scope change seems minor and may not require much effort from the project team, it's important to follow the established change control process. This process ensures that changes are properly evaluated, documented, and approved, preventing uncontrolled changes that can impact project baselines, schedules, and overall project success. Option D is the correct choice as it aligns with best practices in change management. By submitting a formal change request, the project manager can ensure that the change is properly assessed, documented, and approved through the change control process.
upvoted 3 times
...
psvexam
8 months, 4 weeks ago
Ans A The question is clear that the change does not impact the project baseline or schedule. Only if the change goes through Change control process, then it will change the schedule. So what is the point in complicating by going thru D? I would rather select A, just get an approval to implement the change without going through change control process.
upvoted 1 times
...
Community vote distribution
A (35%)
C (25%)
B (20%)
Other
Most Voted
A voting comment increases the vote count for the chosen answer by one.

Upvoting a comment with a selected answer will also increase the vote count towards that answer by one. So if you see a comment that you already agree with, you can upvote it instead of posting a new comment.

SaveCancel
Loading ...