Exam PMP topic 1 question 923 discussion

Actual exam question from PMI's PMP
Question #: 923
Topic #: 1
[All PMP Questions]

A project lead is managing a construction project in an isolated location. There have been delays due to difficult working conditions, which include team sickness and absences.

How should the project lead manage those issues to get the project back on track?

  • A. Ask for additional budget because the project end will be delayed.
  • B. Identify the causes of the issues in order to find a suitable solution.
  • C. Review the project scope in order to simplify it and shorten project duration.
  • D. Ask human resources (HR) to find individuals to replace team members.
Show Suggested Answer Hide Answer
Suggested Answer: B 🗳️

Comments

Chosen Answer:
This is a voting comment (?) , you can switch to a simple comment.
Switch to a voting comment New
victory108
5 days, 18 hours ago
Selected Answer: B
B. Identify the causes of the issues in order to find a suitable solution
upvoted 1 times
...
a81d4bf
5 months, 2 weeks ago
Selected Answer: B
The issues presented in the question could be 2nd and 3rd order effects. Its important to first understand the root causes of those issues to try and alleviate them and reduce their risk prior to making change decisions.
upvoted 1 times
...
517f9da
6 months, 1 week ago
Selected Answer: B
Seeing a lot of randomly voted answers and people providing zero or just weird explanations. Please do your own studying and don't solely rely on others. B. Identify the causes of the issues in order to find a suitable solution. Explanation: Identifying the root causes of the delays allows the project lead to develop targeted solutions to address the specific challenges, such as improving working conditions, implementing health measures, or adjusting schedules, thereby helping to get the project back on track.
upvoted 1 times
...
mmhawish
9 months, 3 weeks ago
Selected Answer: B
In the face of delays caused by difficult working conditions, including team sickness and absences, the project lead should first focus on understanding the root causes of the issues. Option B, identifying the causes to find a suitable solution, is the most appropriate course of action for the following reasons:
upvoted 1 times
...
Trytrio
9 months, 3 weeks ago
Selected Answer: B
The choice between these options depends on the project lead's assessment of the specific situation. If the causes of team sickness and absences are primarily related to factors beyond the project scope (such as external health factors or personal circumstances), Option B may be more appropriate. If there is evidence that scope complexities are a significant contributor to the challenges, Option C could be considered. Ideally, a combination of both options may provide a comprehensive solution: identifying causes (Option B) and, if applicable, adjusting scope (Option C) based on the findings.
upvoted 1 times
...
UppersquareCapital
10 months, 2 weeks ago
Selected Answer: B
Option B suggests a proactive approach, where the project lead should analyze the difficulties, such as team sickness and absences, to understand their origins. By identifying the causes, the project lead can then work on developing suitable solutions to mitigate the challenges and get the project back on track. Options A and C propose addressing the issue by asking for additional budget or reviewing the project scope. While these actions might be necessary in certain situations, they don't directly address the underlying causes of the delays.
upvoted 2 times
...
psvexam
10 months, 4 weeks ago
This is funny! The issues are already listed clearly in the question – sickness, isolated location, difficult working conditions. I don’t understand how B is the right answer – Identifying issues and finding solution. In fact A or C or D seem to be more practical considering the situation of the question.
upvoted 1 times
KennyMuffins
9 months, 3 weeks ago
Why isnt there a need to identify the cause for difficult working conditions, sickness and absences?
upvoted 2 times
...
...
odylec
10 months, 4 weeks ago
Selected Answer: C
C is the answer. it cant be B because you already know the causes. Read the question before you answer
upvoted 1 times
odylec
10 months, 4 weeks ago
Additionally, reviewing the project scope (option C) may help in finding ways to simplify the project or adjust timelines to accommodate the challenges. This approach allows for a more comprehensive and effective strategy in addressing the specific issues mentioned in the question.
upvoted 1 times
...
...
Community vote distribution
A (35%)
C (25%)
B (20%)
Other
Most Voted
A voting comment increases the vote count for the chosen answer by one.

Upvoting a comment with a selected answer will also increase the vote count towards that answer by one. So if you see a comment that you already agree with, you can upvote it instead of posting a new comment.

SaveCancel
Loading ...