Welcome to ExamTopics
ExamTopics Logo
- Expert Verified, Online, Free.
exam questions

Exam PMP All Questions

View all questions & answers for the PMP exam

Exam PMP topic 1 question 1120 discussion

Actual exam question from PMI's PMP
Question #: 1120
Topic #: 1
[All PMP Questions]

A project is starting its third iteration out of six. During planning, the team realized that all of the requirements were not defined clearly enough to start working.

What should the project manager do?

  • A. Review and replace the unclear requirements with ones that are clear.
  • B. Update the issue log and escalate it to the project sponsor.
  • C. Meet with the product owner to review the project backlog.
  • D. Invite key users to the next daily meeting to get requirement clarification.
Show Suggested Answer Hide Answer
Suggested Answer: C 🗳️

Comments

Chosen Answer:
This is a voting comment (?) , you can switch to a simple comment.
Switch to a voting comment New
victory108
3 weeks, 6 days ago
Selected Answer: C
C. Meet with the product owner to review the project backlog
upvoted 1 times
...
sidje
6 months ago
Selected Answer: C
En résumé, rencontrer le Product Owner pour examiner et clarifier le backlog est l'action la plus directe et efficace pour résoudre les problèmes liés à des exigences peu claires.
upvoted 1 times
...
Delab202
10 months, 2 weeks ago
Selected Answer: C
Evolving and discovering requirements. On projects that do not have clearly defined requirements up front, prototypes, demonstrations, storyboards, and mock-ups can be used to evolve the requirements. In these situations, stakeholders are more likely to take an “I’ll know it when I see it” approach to developing requirements. Evolving requirements are common in projects using iterative, incremental, or adaptive development approaches. In some cases, new opportunities arise that change requirements.
upvoted 1 times
Delab202
10 months, 2 weeks ago
Managing requirements. Regardless of whether requirements are documented up front, evolved along the way, or discovered, there is a need to manage them. Ineffective requirements management can lead to rework, scope creep, customer dissatisfaction, budget overruns, schedule delay, and overall project failure. Therefore, many projects have one accountable person for requirements management. This person may serve as business analyst, product owner, value engineer, or other title. Those individuals managing requirements may use specialized software, backlogs, index cards, traceability matrices, or some other method to ensure there is an appropriate level of requirement flexibility versus stability, and that new and changing requirements are agreed to by all relevant stakeholders.
upvoted 1 times
...
...
Abdelmonm
10 months, 2 weeks ago
Selected Answer: C
When facing unclear requirements, it's important to collaborate with the product owner to review and clarify the project backlog. This allows for a better understanding of the requirements and helps in providing the necessary details for the team to proceed with the work. Regular communication with the product owner ensures that requirements are clarified and addressed promptly during the planning and execution phases of the project.
upvoted 1 times
...
kevzzz
10 months, 3 weeks ago
Selected Answer: C
Product owners should review the backlog before each iteration planning meeting to ensure prioritization is correct and feedback from the last iteration has been incorporated. Regular review of the backlog is often called "backlog grooming" in agile circles (some use the term backlog refinement).
upvoted 1 times
...
psvexam
11 months ago
Ans A I don’t know how C is the right answer. First thing to do is to see if there are requirements in backlog that are well defined and can be prioritized for this sprint. If there are none, then you invite the key stakeholders to next daily meeting and make sure you get all the clarifications to move ahead with the backlog for current sprint. So after A, my 2nd choice would be D.
upvoted 1 times
...
Community vote distribution
A (35%)
C (25%)
B (20%)
Other
Most Voted
A voting comment increases the vote count for the chosen answer by one.

Upvoting a comment with a selected answer will also increase the vote count towards that answer by one. So if you see a comment that you already agree with, you can upvote it instead of posting a new comment.

SaveCancel
Loading ...