A company is starting a new agile project with a team that has expertise working on these kinds of projects. During the backlog refinement meeting, the team realizes that they are not completing the estimations because some key information is missing.
What should the project manager do?
victory108
3 weeks, 4 days ago23169fd
1 month, 1 week agoc8ee0e6
4 months, 2 weeks agoNadirJT
7 months, 1 week agoDelab202
10 months, 2 weeks agoAbdelmonm
10 months, 2 weeks agokevzzz
10 months, 3 weeks agoKim222
2 months, 3 weeks agopsvexam
11 months ago