Welcome to ExamTopics
ExamTopics Logo
- Expert Verified, Online, Free.
exam questions

Exam PMP All Questions

View all questions & answers for the PMP exam

Exam PMP topic 1 question 1118 discussion

Actual exam question from PMI's PMP
Question #: 1118
Topic #: 1
[All PMP Questions]

A company is starting a new agile project with a team that has expertise working on these kinds of projects. During the backlog refinement meeting, the team realizes that they are not completing the estimations because some key information is missing.

What should the project manager do?

  • A. Ask to postpone the iteration planning because the estimation is not complete.
  • B. Ask the product owner to review the stories with stakeholders prior to planning.
  • C. Review the project backlog with the product owner before estimating the stories.
  • D. Review the previous project estimations and assign them to the stories.
Show Suggested Answer Hide Answer
Suggested Answer: C 🗳️

Comments

Chosen Answer:
This is a voting comment (?) , you can switch to a simple comment.
Switch to a voting comment New
victory108
3 weeks, 4 days ago
Selected Answer: C
C. Review the project backlog with the product owner before estimating the stories
upvoted 1 times
...
23169fd
1 month, 1 week ago
Selected Answer: B
By reviewing the stories with the relevant stakeholders before the planning meeting, the product owner can ensure that the team has all the necessary information to properly estimate and prioritize the backlog.
upvoted 1 times
...
c8ee0e6
4 months, 2 weeks ago
Selected Answer: B
Since the team is unable to complete estimations due to missing information, the project manager should request that the product owner clarify the requirements with stakeholders before proceeding with estimation and planning. This ensures that the team has a clear understanding of the requirements, enabling them to provide accurate estimates and plan the iteration effectively.
upvoted 2 times
...
NadirJT
7 months, 1 week ago
Selected Answer: B
Only asking product owner to review the stories with the stakeholders prior the backlog refinement can address the solving of such cases in future. Project manager already had meeting with product owner if he is now planning with the team. Stop copy pasting ChatGPT answers here. Answer is B.
upvoted 1 times
...
Delab202
10 months, 2 weeks ago
Selected Answer: C
In this scenario, the project manager should consider option C, which is to review the project backlog with the product owner before estimating the stories. This is a common practice in Agile methodologies like Scrum. Here's why option C is a good choice: C. Review the project backlog with the product owner before estimating the stories:
upvoted 1 times
...
Abdelmonm
10 months, 2 weeks ago
Selected Answer: C
Before estimation, it's essential to have a clear understanding of the user stories and their acceptance criteria. The project manager should collaborate with the product owner to review the project backlog and ensure that the necessary information is available for the team to provide accurate estimations during backlog refinement. This helps in enhancing the accuracy of the estimations and contributes to better planning during the iteration.
upvoted 1 times
...
kevzzz
10 months, 3 weeks ago
Selected Answer: C
The question is referring to the backlog refinement meeting. One key benefit of a backlog refinement session is that it allows teams to have a focused and in-depth discussion about the items in the Product Backlog, to prioritize and refine their understanding of the requirements and goals for each item.
upvoted 2 times
Kim222
2 months, 3 weeks ago
I agree
upvoted 1 times
...
...
psvexam
11 months ago
Ans: B I find some issues with this question which is not framed correctly. Why would team estimate stories in a “backlog refinement”. They would do it in “sprint planning”. There itself, the question is not correct. Secondly, between backlog refining and next sprint planning, the project manager has to ask the [roduct owner to properly review all stories with the stakeholders, get all missing information prior to the next planning. So my choice would be B.
upvoted 1 times
...
Community vote distribution
A (35%)
C (25%)
B (20%)
Other
Most Voted
A voting comment increases the vote count for the chosen answer by one.

Upvoting a comment with a selected answer will also increase the vote count towards that answer by one. So if you see a comment that you already agree with, you can upvote it instead of posting a new comment.

SaveCancel
Loading ...