Exam PMP topic 1 question 1111 discussion

Actual exam question from PMI's PMP
Question #: 1111
Topic #: 1
[All PMP Questions]

During project execution, a project manager discovers that the budget at completion has shifted significantly and is higher than expected. What should the project manager do?

  • A. Perform a root cause analysis of the project performance.
  • B. Adjust the original budget estimates with the current cost variance.
  • C. Review the activity duration to reforecast the project completion date.
  • D. Negotiate the project changes and adjust stakeholder expectations.
Show Suggested Answer Hide Answer
Suggested Answer: A 🗳️

Comments

Chosen Answer:
This is a voting comment (?) , you can switch to a simple comment.
Switch to a voting comment New
victory108
3 weeks, 3 days ago
Selected Answer: A
A. Perform a root cause analysis of the project performance
upvoted 1 times
...
sidje
6 months, 1 week ago
Selected Answer: A
Selon le PMBOK après avoir identifié un problème il est recommandé ensuite de l'analyser avant toute autre chose. Donc la bonne réponse ici c'est le A. Ce n'est qu'après avoir compris le problème que l'une des solutions pourrait être de rencontrer les parties prenantes pour redéfinir le budget.
upvoted 1 times
...
Delab202
10 months, 2 weeks ago
Selected Answer: D
In this situation, the most effective course of action for the project manager is: D. Negotiate the project changes and adjust stakeholder expectations. Here's why the other options might not be optimal: A. Root cause analysis: While understanding the reasons behind the budget overrun is important, it doesn't address the immediate need to manage the increased cost and its impact on the project. B. Adjusting the original budget: Simply increasing the budgeted amount without addressing the reasons or negotiating with stakeholders might not be acceptable and could lead to further issues. C. Reviewing activity duration: Adjusting the timeline might be a potential consequence of budget variance, but it needs to be considered in conjunction with stakeholder negotiation and overall project feasibility. Negotiating project changes and adjusting stakeholder expectations are crucial steps in dealing with a significant budget overrun
upvoted 1 times
...
Abdelmonm
10 months, 2 weeks ago
Selected Answer: A
When the budget at completion has shifted significantly and is higher than expected, it's important for the project manager to perform a root cause analysis. This involves investigating the factors and events that have led to the budget variance. By identifying the root causes, the project manager can address the underlying issues and take corrective actions to bring the project back on track. Adjusting stakeholder expectations and negotiating changes may be part of the response, but understanding the root causes is a crucial first step.
upvoted 4 times
...
psvexam
11 months ago
Ans: D While I do agree, performing root cause analysis is important, but there is an issue at hand. It is already over budget. So what is more important is to negotiate and adjust expectations with stakeholders. So my answer would be D.
upvoted 1 times
arseyam
10 months, 2 weeks ago
To negotiate you need justifications, to have justifications you need to do root cause analysis
upvoted 2 times
...
...
Community vote distribution
A (35%)
C (25%)
B (20%)
Other
Most Voted
A voting comment increases the vote count for the chosen answer by one.

Upvoting a comment with a selected answer will also increase the vote count towards that answer by one. So if you see a comment that you already agree with, you can upvote it instead of posting a new comment.

SaveCancel
Loading ...