Three testers joined the project team just before the end of the build. During the project team meeting, the testers indicated that the project quality is poor, and they should not continue testing until all the defects are fixed.
Which three actions should the project manager do? (Choose three.)
Kim222
2 weeks, 5 days ago517f9da
4 months, 1 week agokmsinthesky
4 months, 1 week ago[Removed]
6 months, 3 weeks agoTrytrio
7 months, 3 weeks agoUppersquareCapital
8 months, 1 week agoUppersquareCapital
8 months, 1 week agoAbdelmonm
8 months, 2 weeks agoodylec
8 months, 3 weeks agocb4a6c4
9 months ago