Three testers joined the project team just before the end of the build. During the project team meeting, the testers indicated that the project quality is poor, and they should not continue testing until all the defects are fixed.

Which three actions should the project manager do? (Choose three.)

  • A. Stop the project and review the output.
  • B. Ask the testers to provide additional information.
  • C. Brainstorm the issue with the project team.
  • D. Continue with testing according to the plan.
  • E. Ask the sponsor for assistance and guidance.
Show Suggested Answer Hide Answer
Suggested Answer: BCD 🗳️

Comments

Chosen Answer:
This is a voting comment (?) , you can switch to a simple comment.
Switch to a voting comment New
victory108
5 days, 13 hours ago
Selected Answer: ABC
A. Stop the project and review the output. B. Ask the testers to provide additional information. C. Brainstorm the issue with the project team.
upvoted 1 times
...
Kim222
2 months, 2 weeks ago
Selected Answer: BCD
BCD is alright
upvoted 1 times
...
517f9da
6 months, 1 week ago
Selected Answer: BCD
B. Ask the testers to provide additional information. C. Brainstorm the issue with the project team. D. Continue with testing according to the plan. Explanation: - **B. Getting detailed information from the testers helps in understanding the specific quality issues and defects. - **C. Collaborating with the project team to identify the root causes of the quality issues and develop a plan to address them. - **D. Proceeding with testing ensures that all issues are identified, allowing the team to prioritize and fix defects based on the overall project timeline and quality objectives. D is important to do because you need to attempt to identify all the defects with complete testing. THEN you can do what's appropriate to fix everything that is identified. Make sense?
upvoted 1 times
...
kmsinthesky
6 months, 2 weeks ago
Selected Answer: ABC
ABC, D cannot since fail should be fixed for futher testing. E. quality should be fixed first.
upvoted 1 times
...
[Removed]
8 months, 3 weeks ago
Selected Answer: BCE
The question says "they should not continue testing until all the defects are fixed". So I can choose option D. And option A is also no option, so I have BCE.
upvoted 2 times
...
Trytrio
9 months, 3 weeks ago
Selected Answer: BCD
its BCD
upvoted 1 times
...
UppersquareCapital
10 months, 2 weeks ago
Selected Answer: BCD
B. Ask the testers to provide additional information: The project manager should gather more information from the testers to understand the nature and severity of the quality issues. This will help in making informed decisions on how to address the concerns. C. Brainstorm the issue with the project team: Engaging the entire project team in a brainstorming session can help identify the root causes of the quality issues and generate potential solutions. It encourages collaboration and leverages the collective knowledge and expertise of the team. D. Continue with testing according to the plan: While addressing quality issues is essential, it's also important to stick to the project plan. The project manager may decide to continue testing as planned while concurrently addressing and fixing the identified defects. This ensures that the project continues to progress while quality concerns are being addressed.
upvoted 1 times
UppersquareCapital
10 months, 2 weeks ago
Options A and E are not recommended in this context: A. Stopping the project and reviewing the output may cause unnecessary delays and might be an extreme measure, especially if there are ways to address the issues without halting the entire project. E. Involving the sponsor may be premature at this stage. It's often more effective to first gather information, engage the project team, and assess the situation before escalating to higher levels.
upvoted 1 times
...
...
Abdelmonm
10 months, 2 weeks ago
Selected Answer: BCE
Certainly, here are three concise actions: Ask the testers for more information: Engage with the testing team to understand the nature and severity of identified defects and gather additional information about quality concerns. Brainstorm the issue with the project team: Conduct a collaborative discussion with the entire project team to identify root causes of poor quality and involve team members in problem-solving. Seek sponsor assistance and guidance: Communicate the situation to the project sponsor, providing an overview of the issues and actions taken, and seek guidance or support as needed.
upvoted 2 times
...
odylec
10 months, 4 weeks ago
Selected Answer: BCD
BCD is the answer
upvoted 2 times
...
cb4a6c4
11 months ago
Selected Answer: ABC
Stop--ask more details-brainstorm. Stopping the project may lead to delay but better to focus on the fix rather than continue doing poor quality work.
upvoted 2 times
...
Community vote distribution
A (35%)
C (25%)
B (20%)
Other
Most Voted
A voting comment increases the vote count for the chosen answer by one.

Upvoting a comment with a selected answer will also increase the vote count towards that answer by one. So if you see a comment that you already agree with, you can upvote it instead of posting a new comment.

SaveCancel
Loading ...