Welcome to ExamTopics
ExamTopics Logo
- Expert Verified, Online, Free.
exam questions

Exam PMP All Questions

View all questions & answers for the PMP exam

Exam PMP topic 1 question 1008 discussion

Actual exam question from PMI's PMP
Question #: 1008
Topic #: 1
[All PMP Questions]

A product owner is trying to understand how many of the user stones have been completed within a 2-week sprint. How should the project manager approach this situation?

  • A. Use retrospectives to deliver the finished products.
  • B. Invite the product owner to regular standup meetings.
  • C. Have a face-to-face conversation with the product owner.
  • D. Share the burndown chart with the product owner.
Show Suggested Answer Hide Answer
Suggested Answer: D 🗳️

Comments

Chosen Answer:
This is a voting comment (?) , you can switch to a simple comment.
Switch to a voting comment New
Any_Nick_Name
Highly Voted 11 months, 1 week ago
burndown is for the remaining stories, burnup is for the completed stories...answer cannot be D!!
upvoted 5 times
sweety433
5 months, 1 week ago
Agree that Burndown chart is to check the remaining work left and burnup for the completed work. However, A,B,C looks not relevant. And with Burndown chart we can understand the left over work so we can understand what was completed already based on the Burndown chart. I feel most relevant and close answer is D
upvoted 1 times
...
...
victory108
Most Recent 1 month, 1 week ago
Selected Answer: D
D. Share the burndown chart with the product owner
upvoted 1 times
...
martinx84
4 months, 3 weeks ago
Selected Answer: D
Share burndown chart
upvoted 1 times
...
517f9da
6 months, 2 weeks ago
Selected Answer: D
D. Share the burndown chart with the product owner Sharing the burndown chart provides a clear visual representation of the progress made during the sprint, helping the product owner understand how many user stories have been completed.
upvoted 1 times
...
[Removed]
8 months, 4 weeks ago
Selected Answer: D
What are user stones? :-)
upvoted 2 times
...
Ginairo214
9 months, 2 weeks ago
Selected Answer: D
According to PMBOK 7th Edition, 4.6.6 Visual Data and Information Burndown/Burnup Chart: This chart is a graphical representation of the work remaining in a timebox or the work completed toward the release of a product or project deliverable. So option D is the correct answer.
upvoted 1 times
...
Trytrio
9 months, 3 weeks ago
Selected Answer: D
To help the product owner understand how many of the user stories have been completed within a 2-week sprint, the project manager should share the burndown chart with the product owner (Option D). The burndown chart is a visual tool that shows the amount of work completed and the work remaining in a sprint, providing a clear and concise update on the progress of user stories. It's an effective way to communicate this information to the product owner.
upvoted 1 times
...
UppersquareCapital
10 months, 1 week ago
Selected Answer: D
In Agile methodologies, particularly Scrum, the burndown chart is a visual representation of the progress made during a sprint. It shows the amount of work remaining versus time. Sharing the burndown chart with the product owner is an effective way to provide a clear, visual overview of the progress of user stories within the sprint. The burndown chart allows the product owner to see how much work has been completed and how much is remaining, helping them to understand the team's progress toward achieving the sprint goals. It provides transparency and helps facilitate communication between the development team and the product owner.
upvoted 1 times
...
Abdelmonm
10 months, 2 weeks ago
Selected Answer: D
In agile project management, the burndown chart is a visual representation of work completed over time. It provides a snapshot of the team's progress in completing user stories or tasks during a sprint. Sharing the burndown chart with the product owner allows them to see the progress made during the sprint, understand how many user stories have been completed, and track whether the team is on target to meet the sprint goals. This promotes transparency and collaboration between the development team and the product owner in monitoring and managing the sprint progress.
upvoted 1 times
...
chlaithem
10 months, 2 weeks ago
the most effective approach likely involves a combination of C and D: Schedule a brief face-to-face conversation with the product owner: Discuss the specific completed user stories, their functionalities, and any potential impacts or decisions needed. Share the burndown chart as supplementary information: This provides a visual representation of overall progress and facilitates further discussion if the product owner needs more in-depth details.
upvoted 1 times
...
ced45c8
10 months, 3 weeks ago
Selected Answer: B
most probable answer is B, although still doesn't makes sense to me but it is the best option out of all
upvoted 1 times
...
Samtx99
11 months, 1 week ago
A burndown chart shows the amount of work that has been completed in an epic or sprint. So I D seems more appropriate.
upvoted 1 times
...
Community vote distribution
A (35%)
C (25%)
B (20%)
Other
Most Voted
A voting comment increases the vote count for the chosen answer by one.

Upvoting a comment with a selected answer will also increase the vote count towards that answer by one. So if you see a comment that you already agree with, you can upvote it instead of posting a new comment.

SaveCancel
Loading ...