You work as a program manager for a large construction program. Your program includes constructing hotels across the country. You collect information on the status of the program. During comparison with the original plan you find the 200 hotels have been completed as against 275 hotels planned as of today. In which program process are you working on?

  • A. Monitor and Control Program Scope
  • B. Monitor and Control Project Performance
  • C. Monitor and Control Program Schedule
  • D. Manage Program Issues
Show Suggested Answer Hide Answer
Suggested Answer: C 🗳️

Comments

Chosen Answer:
This is a voting comment (?). It is better to Upvote an existing comment if you don't have anything to add.
Switch to a voting comment New
happykaur
8 months, 1 week ago
Selected Answer: C
Program schedule monitoring and controlling is the activity of ensuring the program produces the required capabilities and benefits on time. This activity includes tracking and monitoring the start and finish of all high-level component and program activities and milestones against the program master schedule planned timelines. Updating the program master schedule and directing changes to individual component schedules is required to maintain an accurate and upto- date program master schedule.
upvoted 1 times
...
happykaur
8 months, 1 week ago
Selected Answer: B
Monitoring and controlling activities are performed by both program- and project-level components during delivery management. These activities include collecting, measuring, and disseminating performance information to track progress against the program objectives and assess overall program trends. Continuous monitoring gives the program management team insight into the current health of the program and identifies areas that require special attention. Monitoring activities determine if and when controlling activities, such as corrective or preventive action, are needed to bring the program back in alignment with the strategic priorities
upvoted 1 times
...
[Removed]
10 months ago
Selected Answer: C
C. Monitor and Control Program Schedule
upvoted 1 times
...
[Removed]
10 months, 2 weeks ago
Selected Answer: C
Monitor and Control Program Schedule. Monitoring and controlling the program schedule involves tracking the actual progress against the planned schedule and taking corrective actions if there are deviations. In your case, reviewing the number of hotels completed against the scheduled plan directly pertains to schedule management, as it reflects how the program is adhering to its timeline. This process is essential for ensuring that the program remains on track to meet its objectives within the designated time frames.
upvoted 1 times
[Removed]
10 months, 2 weeks ago
Recommended answer is about PROJECT not PROGRAM
upvoted 1 times
...
...
Community vote distribution
A (35%)
C (25%)
B (20%)
Other
Most Voted
A voting comment increases the vote count for the chosen answer by one.

Upvoting a comment with a selected answer will also increase the vote count towards that answer by one. So if you see a comment that you already agree with, you can upvote it instead of posting a new comment.

SaveCancel
Loading ...
exam
Someone Bought Contributor Access for:
SY0-701
London, 1 minute ago