Exam PgMP topic 1 question 190 discussion

Actual exam question from PMI's PgMP
Question #: 190
Topic #: 1
[All PgMP Questions]

Robert is the program manager for his organization which operates in a matrix structure.
Resources in Robert's program will be utilized on several projects in and out of his program. He wants to be certain that all of the resources will be planned accordingly and that the project managers communicate with one another about when the resources will be needed and utilized in the projects. What plan should
Robert create along with the project managers to ensure that the resources are scheduled and managed effectively?

  • A. Resource management plan
  • B. Program management calendar
  • C. Schedule management plan
  • D. Resource calendar
Show Suggested Answer Hide Answer
Suggested Answer: A 🗳️

Comments

Chosen Answer:
This is a voting comment (?). It is better to Upvote an existing comment if you don't have anything to add.
Switch to a voting comment New
tungdt
9 months ago
A is correct A Resource Management Plan outlines how resources will be identified, acquired, and managed throughout the program. This plan includes details about resource allocation, scheduling, responsibilities, and communication strategies among project managers to ensure that resources are utilized efficiently and conflicts are minimized. It helps in planning and coordinating the use of resources across multiple projects, ensuring that all project needs are met in a timely and organized manner.
upvoted 1 times
...
[Removed]
1 year, 3 months ago
A. Resource Management Plan. The Resource Management Plan is a key document in program and project management that outlines how resources will be estimated, acquired, managed, and controlled. In a matrix organization where resources are shared across multiple projects, this plan is crucial. It would detail the allocation of resources, the timing of their usage, and the coordination among different project managers to ensure that resource availability aligns with project needs. The plan helps in avoiding conflicts and over-allocation of resources, thereby facilitating smooth execution of projects within the program.
upvoted 1 times
...
Community vote distribution
A (35%)
C (25%)
B (20%)
Other
Most Voted
A voting comment increases the vote count for the chosen answer by one.

Upvoting a comment with a selected answer will also increase the vote count towards that answer by one. So if you see a comment that you already agree with, you can upvote it instead of posting a new comment.

SaveCancel
Loading ...
exam
Someone Bought Contributor Access for:
SY0-701
London, 1 minute ago