A project manager is in charge of a software development project. A key stakeholder complains that they never received the functionality test status reports. The project manager provides the reports, and the stakeholder notices that an important functionality for their area was not tested.
Which tool should the project manager have used to prevent this situation?
27b2ada
1 week, 5 days agoKim222
3 weeks agoc8ee0e6
2 months, 1 week agoLNX_RM_Admin
4 months ago[Removed]
6 months, 3 weeks agommhawish
7 months, 2 weeks agoTrytrio
7 months, 2 weeks agodinodragon
3 months agoKennyMuffins
7 months, 3 weeks agoDavard
7 months, 4 weeks agomesacgon
8 months agoDelab202
8 months, 1 week agoMoyWH
8 months, 2 weeks agoAbdelmonm
8 months, 2 weeks agogsap
9 months, 1 week ago