A project manager is in charge of a software development project. A key stakeholder complains that they never received the functionality test status reports. The project manager provides the reports, and the stakeholder notices that an important functionality for their area was not tested.
Which tool should the project manager have used to prevent this situation?
victory108
1 month ago27b2ada
2 months, 2 weeks agoKim222
2 months, 3 weeks agoc8ee0e6
4 months, 2 weeks agoLNX_RM_Admin
6 months, 1 week ago[Removed]
8 months, 4 weeks agommhawish
9 months, 2 weeks agoTrytrio
9 months, 3 weeks agodinodragon
5 months, 1 week agoKennyMuffins
9 months, 3 weeks agoDavard
10 months agomesacgon
10 months, 1 week agoDelab202
10 months, 1 week agoMoyWH
10 months, 3 weeks agoAbdelmonm
10 months, 3 weeks agogsap
11 months, 1 week ago