A project manager is monitoring and recording results of executing the quality management activities to assess performance and ensure the project outputs are complete, correct, and meet customer expectations.
Which output is the project manager using?

  • A. Approved change requests
  • B. Verified deliverables
  • C. Lessons learned
  • D. Work performance data
Show Suggested Answer Hide Answer
Suggested Answer: B 🗳️

Comments

Chosen Answer:
This is a voting comment (?). It is better to Upvote an existing comment if you don't have anything to add.
Switch to a voting comment New
041ba31
10 months, 1 week ago
B. Verified deliverables In this scenario, the project manager is monitoring and recording the results of executing the quality management activities to assess performance and ensure that the project outputs (deliverables) are complete, correct, and meet customer expectations. The output being used is "Verified deliverables." Verified deliverables are project deliverables that have undergone the quality control process and have been validated to meet the required quality standards and specifications.
upvoted 1 times
...
Community vote distribution
A (35%)
C (25%)
B (20%)
Other
Most Voted
A voting comment increases the vote count for the chosen answer by one.

Upvoting a comment with a selected answer will also increase the vote count towards that answer by one. So if you see a comment that you already agree with, you can upvote it instead of posting a new comment.

SaveCancel
Loading ...
exam
Someone Bought Contributor Access for:
SY0-701
London, 1 minute ago