Welcome to ExamTopics
ExamTopics Logo
- Expert Verified, Online, Free.
exam questions

Exam CAPM All Questions

View all questions & answers for the CAPM exam

Exam CAPM topic 1 question 256 discussion

Actual exam question from PMI's CAPM
Question #: 256
Topic #: 1
[All CAPM Questions]

A project manager proactively meets with other project managers who manage other projects in the same program. To minimize the impact that other projects within the program may have on their project, of what should the project manager be aware?

  • A. Demands on the same resources
  • B. Requirements that impact the scope
  • C. Uncertainty of emerging issues
  • D. Project charter
Show Suggested Answer Hide Answer
Suggested Answer: A 🗳️

Comments

Chosen Answer:
This is a voting comment (?) , you can switch to a simple comment.
Switch to a voting comment New
Vangelis_1980
1 month, 3 weeks ago
Selected Answer: A
A. Demands on the same resources By proactively meeting with other project managers, the project manager can identify potential conflicts or competition for shared resources, such as: Human resources: Overlapping skill sets or team members. Equipment: Shared tools or machinery. Budget: Competing for limited funds. Understanding these demands upfront allows for effective resource planning, negotiation, and potential mitigation strategies.
upvoted 1 times
...
041ba31
9 months, 1 week ago
A. Demands on the same resources To minimize the impact that other projects within the same program may have on their project, the project manager should be aware of the demands on the same resources. In a program environment, multiple projects often share common resources, such as personnel, equipment, or facilities. If these resources are overallocated or not available when needed due to conflicts with other projects, it can negatively impact the project's schedule, cost, and overall success. Therefore, effective resource management and coordination with other project managers in the program are crucial to mitigate resource-related risks.
upvoted 1 times
...
Community vote distribution
A (35%)
C (25%)
B (20%)
Other
Most Voted
A voting comment increases the vote count for the chosen answer by one.

Upvoting a comment with a selected answer will also increase the vote count towards that answer by one. So if you see a comment that you already agree with, you can upvote it instead of posting a new comment.

SaveCancel
Loading ...