B. Cost performance index (CPI)
The cost performance index (CPI) is the earned value (EV) measure that indicates the cost efficiency of the work completed on a project. It is calculated by dividing the earned value (EV) by the actual cost (AC). The CPI value greater than 1 indicates that the project is under budget and that the work is being performed efficiently. A CPI less than 1 suggests that the project is over budget and that the work is not being performed as efficiently as planned.
upvoted 2 times
...
This section is not available anymore. Please use the main Exam Page.CAPM Exam Questions
Log in to ExamTopics
Sign in:
Community vote distribution
A (35%)
C (25%)
B (20%)
Other
Most Voted
A voting comment increases the vote count for the chosen answer by one.
Upvoting a comment with a selected answer will also increase the vote count towards that answer by one.
So if you see a comment that you already agree with, you can upvote it instead of posting a new comment.
041ba31
10 months, 1 week ago