exam questions

Exam CAPM All Questions

View all questions & answers for the CAPM exam

Exam CAPM topic 1 question 266 discussion

Actual exam question from PMI's CAPM
Question #: 266
Topic #: 1
[All CAPM Questions]

What earned value (EV) measure indicates the cost efficiency of the work completed?

  • A. Cost variance (CV)
  • B. Cost performance index (CPI)
  • C. To-complete performance index (TCPI)
  • D. Variance at completion (VAC)
Show Suggested Answer Hide Answer
Suggested Answer: B 🗳️

Comments

Chosen Answer:
This is a voting comment (?). It is better to Upvote an existing comment if you don't have anything to add.
Switch to a voting comment New
041ba31
10 months, 1 week ago
B. Cost performance index (CPI) The cost performance index (CPI) is the earned value (EV) measure that indicates the cost efficiency of the work completed on a project. It is calculated by dividing the earned value (EV) by the actual cost (AC). The CPI value greater than 1 indicates that the project is under budget and that the work is being performed efficiently. A CPI less than 1 suggests that the project is over budget and that the work is not being performed as efficiently as planned.
upvoted 2 times
...
Community vote distribution
A (35%)
C (25%)
B (20%)
Other
Most Voted
A voting comment increases the vote count for the chosen answer by one.

Upvoting a comment with a selected answer will also increase the vote count towards that answer by one. So if you see a comment that you already agree with, you can upvote it instead of posting a new comment.

SaveCancel
Loading ...
exam
Someone Bought Contributor Access for:
SY0-701
London, 1 minute ago