You are the program manager of the NQA Program. In this program you're planning which contract types you'll allow into the program and which ones you will not.
One contract type you won't accept is the cost plus percentage of cost contract. Which of the following is a valid reason you would not allow this contract type into your program?

  • A. The contract type requires the vendor to provide a fee for the time invested and the materials used.
  • B. The contract type allows the vendor to change the price of the work he's completed.
  • C. The contract type allows is the most dangerous for the buyer.
  • D. The contract type requires the vendor to provide a fixed price for the work.
Show Suggested Answer Hide Answer
Suggested Answer: C 🗳️

Comments

Chosen Answer:
This is a voting comment. You can switch to a simple comment. It is better to Upvote an existing comment if you don't have anything to add.
Switch to a voting comment New
tungdt
9 months, 1 week ago
Yes, C is correct
upvoted 1 times
...
[Removed]
1 year, 3 months ago
C. The contract type is the most dangerous for the buyer. A cost plus percentage of cost contract can be risky for the buyer (in this case, your program) because it provides little incentive for the contractor to control costs. Under this type of contract, the contractor is reimbursed for all legitimate costs incurred during the project plus a percentage of these costs as profit. This means the more the contractor spends, the more profit they make, which can lead to inefficiencies and inflated costs, potentially causing financial risks for the program.
upvoted 1 times
...
Community vote distribution
A (35%)
C (25%)
B (20%)
Other
Most Voted
A voting comment increases the vote count for the chosen answer by one.

Upvoting a comment with a selected answer will also increase the vote count towards that answer by one. So if you see a comment that you already agree with, you can upvote it instead of posting a new comment.

SaveCancel
Loading ...
exam
Someone Bought Contributor Access for:
MS-102
Bucharest, 1 minute ago