A project is in the planning phase. The project manager notices that the available engineers do not have the required skills. Since outsourcing is not an option for this project, the project manager asks human resources (HR) to hire or assign engineers with the required skills. However, the company cannot afford this at the moment.
What should the project manager do first?
victory108
3 weeks, 1 day agoc8ee0e6
4 months, 2 weeks agoAzharmak
4 months, 2 weeks agoompk
6 months, 2 weeks agoAditech
7 months, 2 weeks agohoomz
9 months agoVictory007
10 months, 1 week agoDelab202
10 months, 2 weeks agoAbdelmonm
10 months, 2 weeks agoced45c8
10 months, 2 weeks agokevzzz
10 months, 3 weeks agopsvexam
11 months agoJaya12
11 months, 2 weeks ago