Actual exam question from PMI's PMP
Question #: 1131
Topic #: 1
[All PMP Questions]

A senior project manager is assigned to lead a team of project managers to run a large initiative. One of the key stakeholders often bypasses the senior project manager and girves instructions to the other project managers directly.

What should the senior project manager do?

  • A. Tell the project managers to document the stakeholder’s instructions.
  • B. Evaluate the stakeholder analysis to identify the stakeholder’s influence.
  • C. Review the benefits realization plan with the sponsor and the stakeholder.
  • D. Escalate to the project sponsors and the manager of this stakeholder.
Show Suggested Answer Hide Answer
Suggested Answer: B 🗳️

Comments

Chosen Answer:
This is a voting comment (?) , you can switch to a simple comment.
Switch to a voting comment New
victory108
3 weeks, 1 day ago
Selected Answer: B
B. Evaluate the stakeholder analysis to identify the stakeholder’s influence
upvoted 1 times
...
Azharmak
4 months, 2 weeks ago
B. Evaluate the stakeholder analysis to identify the stakeholder’s influence. By evaluating the stakeholder analysis, the senior project manager can better understand the stakeholder’s influence, motives, and potential impact on the project. This insight can help in addressing the behavior appropriately
upvoted 1 times
...
dinodragon
5 months ago
Going with B just because escalation without any discussion or analysis is not a good idea.
upvoted 1 times
...
UppersquareCapital
6 months ago
Selected Answer: B
Escalation should be a later step after understanding the stakeholder's influence and attempting to manage the situation directly.
upvoted 1 times
...
sidje
6 months ago
Selected Answer: D
En escaladant le problème auprès des sponsors du projet et du gestionnaire de la partie prenante, le chef de projet senior peut clarifier les rôles et responsabilités, et s'assurer que les communications passent par les canaux appropriés. Cela aidera à rétablir l'autorité du chef de projet principal et à améliorer la coordination et la gestion de projet.
upvoted 1 times
...
[Removed]
8 months, 3 weeks ago
Selected Answer: C
We know already that it is a key stakeholder, so it seems we know that his influence is high. Therefore it is not B. I have also with D a problem, because I want to solve the conflict in other ways. I choose C, I want to speak with the sponsor and the key stakeholder, and I want their commitment that they agree to the realization plan. If they agree, then I hope the key stakeholder will not longer bypasses the senior project manager, because he has agreed to the plan.
upvoted 1 times
...
Trytrio
9 months, 3 weeks ago
B - stakeholders always gets assessed first
upvoted 2 times
...
Abdelmonm
10 months, 2 weeks ago
Selected Answer: D
In this situation, where a key stakeholder is bypassing the senior project manager and giving instructions directly to other project managers, it's essential to address the issue through escalation. Escalating the matter to the project sponsors and the manager of the stakeholder will help bring attention to the situation and seek a resolution at a higher level. This ensures that proper communication channels and project management hierarchy are respected, and it may lead to a more effective resolution of the issue.
upvoted 2 times
...
kevzzz
10 months, 3 weeks ago
Selected Answer: B
The senior PM needs to know where this stakeholder's place is in the world he can make the appropriate approach to the situation.
upvoted 1 times
...
psvexam
11 months ago
Ans A I would vote for A. Everything should be documented to use for future analysis or escalations etc. Unless it is a distraction to the project managers or they are losing their time for other planned activities, I dont see a concern.
upvoted 1 times
...
Jaya12
11 months, 2 weeks ago
Selected Answer: B
This approach will allow the senior project manager to gain insights into the stakeholder's influence and motivations, helping in developing a more tailored strategy to address the situation effectively.
upvoted 1 times
...
Ella008
11 months, 2 weeks ago
B: Analyze first
upvoted 1 times
...
Community vote distribution
A (35%)
C (25%)
B (20%)
Other
Most Voted
A voting comment increases the vote count for the chosen answer by one.

Upvoting a comment with a selected answer will also increase the vote count towards that answer by one. So if you see a comment that you already agree with, you can upvote it instead of posting a new comment.

SaveCancel
Loading ...