Welcome to ExamTopics
ExamTopics Logo
- Expert Verified, Online, Free.
exam questions

Exam PMP All Questions

View all questions & answers for the PMP exam

Exam PMP topic 1 question 1091 discussion

Actual exam question from PMI's PMP
Question #: 1091
Topic #: 1
[All PMP Questions]

A project manager held a meeting and framed the project schedule. A critical stakeholder, who was not consulted at the time of the schedule discussion, complained that the published dates are not agreeable due to a prescheduled task for another assignment.

What should the project manager do first?

  • A. Organize a new schedule framing meeting with the critical stakeholder to obtain input.
  • B. Discuss with the project sponsor and create a new project schedule.
  • C. Analyze the root cause of the issue and update the communications management plan.
  • D. Reach out to the project sponsor and request additional resources.
Show Suggested Answer Hide Answer
Suggested Answer: A 🗳️

Comments

Chosen Answer:
This is a voting comment (?) , you can switch to a simple comment.
Switch to a voting comment New
deviszont
Highly Voted 11 months, 2 weeks ago
Selected Answer: C
If we are taling about the FIRST step the PM needs to take: from my perspective it has to be investigated why a critical stakeholder was not consulted and this issue has to be corrected. Then the second step the PM needs to take: he/she needs to organize new schedule framing meeting with the critical stakeholder.
upvoted 8 times
...
victory108
Most Recent 4 weeks ago
Selected Answer: A
A. Organize a new schedule framing meeting with the critical stakeholder to obtain input
upvoted 1 times
...
Kim222
3 months, 2 weeks ago
Selected Answer: A
If key stakeholders say the schedule is not in line, the schedule must be renegotiated in some way.
upvoted 1 times
...
c8ee0e6
4 months, 2 weeks ago
Selected Answer: A
The correct answer is A. Organize a new schedule framing meeting with the critical stakeholder to obtain input. When a critical stakeholder complains that the published dates are not agreeable due to a prescheduled task for another assignment, the project manager should first consult with the stakeholder to understand their concerns and requirements. This meeting will allow the project manager to: 1. Understand the stakeholder's constraints and limitations. 2. Discuss possible alternatives and adjustments to the project schedule. 3. Obtain the stakeholder's input and agreement on the revised schedule. Only after consulting with the critical stakeholder should the project manager consider updating the project schedule, communicating changes to other stakeholders, and potentially involving the project sponsor or adjusting the communications management plan.
upvoted 1 times
...
Pmpjune152024
5 months, 2 weeks ago
Selected Answer: A
While analyzing the root cause of the issue and updating the communications management plan (option C) is an important task for continuous improvement, it does not directly address the immediate problem: the critical stakeholder's concern about the project schedule. The primary objective at this point is to ensure that the stakeholder's concerns are addressed and that the project schedule is feasible for all parties involved. Organizing a new schedule framing meeting with the critical stakeholder (option A) is the most direct and effective way to do this. Once the meeting has been held, and the schedule has been adjusted, the project manager can then analyze the root cause of the communication breakdown and update the communications management plan accordingly (option C) to prevent similar issues from occurring in the future.
upvoted 1 times
...
ompk
5 months, 4 weeks ago
C first to see why that critical stakeholder wasnt involved in scheduling discussions, then A
upvoted 1 times
...
dimo475
8 months, 1 week ago
C Those kinds of questions are without meaning. They dont offer knowledge. I say C but I think that it's a meaningless question.
upvoted 1 times
...
KennyMuffins
8 months, 4 weeks ago
Selected Answer: A
Question states "do first" = immediate proactive action to resolve the situation. Rather than RCA, engaging the stakeholder is the most immediate action to take to resolve the issue at hand.
upvoted 2 times
PeterCK
7 months, 1 week ago
Agree, both A and C should be do by this situation. but A should "Do First" then C later.
upvoted 1 times
...
...
hoomz
9 months, 1 week ago
Selected Answer: A
While a proactive measure for the future, understanding the root cause doesn't immediately fix the scheduling clash and further delays resolution.
upvoted 1 times
...
Davard
10 months ago
Selected Answer: A
Analyzing the root cause of the issue and updating the communications management plan (option C) may be relevant for addressing communication gaps or issues, but the immediate priority is to address the stakeholder's concerns regarding the project schedule.
upvoted 4 times
...
Abdelmonm
10 months, 2 weeks ago
Selected Answer: A
By involving the critical stakeholder in a new schedule framing meeting, the project manager can gather their input and considerations, ensuring that their schedule constraints and commitments are taken into account. This promotes collaboration and helps in creating a more realistic and feasible project schedule.
upvoted 2 times
...
Jaya12
11 months, 2 weeks ago
Selected Answer: C
This approach involves investigating why the critical stakeholder was not consulted during the schedule framing meeting. Understanding and rectifying this root cause will help prevent similar oversights in the future, improving stakeholder engagement practices.
upvoted 2 times
...
Community vote distribution
A (35%)
C (25%)
B (20%)
Other
Most Voted
A voting comment increases the vote count for the chosen answer by one.

Upvoting a comment with a selected answer will also increase the vote count towards that answer by one. So if you see a comment that you already agree with, you can upvote it instead of posting a new comment.

SaveCancel
Loading ...