A project manager held a meeting and framed the project schedule. A critical stakeholder, who was not consulted at the time of the schedule discussion, complained that the published dates are not agreeable due to a prescheduled task for another assignment.
What should the project manager do first?
deviszont
Highly Voted 11 months, 2 weeks agovictory108
Most Recent 4 weeks agoKim222
3 months, 2 weeks agoc8ee0e6
4 months, 2 weeks agoPmpjune152024
5 months, 2 weeks agoompk
5 months, 4 weeks agodimo475
8 months, 1 week agoKennyMuffins
8 months, 4 weeks agoPeterCK
7 months, 1 week agohoomz
9 months, 1 week agoDavard
10 months agoAbdelmonm
10 months, 2 weeks agoJaya12
11 months, 2 weeks ago