Welcome to ExamTopics
ExamTopics Logo
- Expert Verified, Online, Free.
exam questions

Exam PMP All Questions

View all questions & answers for the PMP exam

Exam PMP topic 1 question 1116 discussion

Actual exam question from PMI's PMP
Question #: 1116
Topic #: 1
[All PMP Questions]

In an agile project, the team planned to complete 40 story points in an iteration, but only completed 30 story points. What is the schedule performance index (SPI)?

  • A. 30/40
  • B. 30/70
  • C. 40/30
  • D. 40/70
Show Suggested Answer Hide Answer
Suggested Answer: A 🗳️

Comments

Chosen Answer:
This is a voting comment (?) , you can switch to a simple comment.
Switch to a voting comment New
victory108
3 weeks, 3 days ago
Selected Answer: A
A. 30/40
upvoted 1 times
...
sidje
6 months ago
SPI = PV/EV = 30/40 = 0,7
upvoted 1 times
...
Aditech
7 months, 2 weeks ago
A The Schedule Performance Index (SPI) measures the efficiency of a project team in meeting the planned schedule. It is calculated by dividing the Earned Value (EV) by the Planned Value (PV). In this case: - Planned Value (PV) = 40 story points - Earned Value (EV) = 30 story points So, SPI = EV / PV = 30 / 40 = 0.75 Therefore, the Schedule Performance Index (SPI) is 0.75. This means that for every planned story point, the team only completed 0.75 points, indicating a schedule performance slightly below the planned target. Final Answer =30/40. Adigun.
upvoted 2 times
...
UppersquareCapital
10 months, 1 week ago
Selected Answer: A
The Schedule Performance Index (SPI) is a measure of schedule efficiency and is calculated as the ratio of earned value to planned value. SPI = Earned Value / Planned Value. In this case, the earned value is the actual work completed, which is 30 story points, and the planned value is the work that was originally planned, which is 40 story points. So, the SPI is: SPI = 30 / 40
upvoted 2 times
...
Abdelmonm
10 months, 2 weeks ago
Selected Answer: A
The Schedule Performance Index (SPI) is calculated by dividing the Earned Value (EV) by the Planned Value (PV). The formulas are as follows: SPI= PV/EV In an agile project context, story points are often used as a measure of work. If the team planned to complete 40 story points (PV) in an iteration but only completed 30 story points (EV), the SPI can be calculated as: SPI= 30/40
upvoted 1 times
...
gsap
11 months, 2 weeks ago
Selected Answer: A
SPI = EV/PV = 30/40
upvoted 3 times
...
Community vote distribution
A (35%)
C (25%)
B (20%)
Other
Most Voted
A voting comment increases the vote count for the chosen answer by one.

Upvoting a comment with a selected answer will also increase the vote count towards that answer by one. So if you see a comment that you already agree with, you can upvote it instead of posting a new comment.

SaveCancel
Loading ...