A project is nearing the completion of a sprint when the product owner announces that a local regulator has banned part of the deliverable. What should the project manager do?
A.
Complete the sprint and seek a waiver from the regulator.
B.
Perform a sprint risk assessment and analyze challenges.
C.
Add more items to the sprint backlog that will add value.
D.
Complete the sprint, but do not release the deliverable.
B. Perform a sprint risk assessment and analyze challenges.
Explanation: Conducting a sprint risk assessment and analyzing the challenges posed by the new regulation allows the project manager to understand the impact, identify potential solutions, and adjust the project plan accordingly. This proactive approach helps in making informed decisions on how to proceed with the deliverable and ensures compliance with regulatory requirements.
B is the answer. Considering the urgency and potential impact on the project, option B (Perform a sprint risk assessment and analyze challenges) seems to be a reasonable approach. This would allow the project manager to gather information, assess the risks, and make informed decisions about how to proceed in light of the regulator's ban.
b: Perform a risk sprint assessment and analyze challenges
upvoted 1 times
...
Log in to ExamTopics
Sign in:
Community vote distribution
A (35%)
C (25%)
B (20%)
Other
Most Voted
A voting comment increases the vote count for the chosen answer by one.
Upvoting a comment with a selected answer will also increase the vote count towards that answer by one.
So if you see a comment that you already agree with, you can upvote it instead of posting a new comment.
victory108
5 days, 13 hours ago517f9da
6 months, 1 week agoodylec
10 months, 4 weeks agoElla008
11 months, 2 weeks ago