Welcome to ExamTopics
ExamTopics Logo
- Expert Verified, Online, Free.
exam questions

Exam PMP All Questions

View all questions & answers for the PMP exam

Exam PMP topic 1 question 931 discussion

Actual exam question from PMI's PMP
Question #: 931
Topic #: 1
[All PMP Questions]

A project is nearing the completion of a sprint when the product owner announces that a local regulator has banned part of the deliverable. What should the project manager do?

  • A. Complete the sprint and seek a waiver from the regulator.
  • B. Perform a sprint risk assessment and analyze challenges.
  • C. Add more items to the sprint backlog that will add value.
  • D. Complete the sprint, but do not release the deliverable.
Show Suggested Answer Hide Answer
Suggested Answer: B 🗳️

Comments

Chosen Answer:
This is a voting comment (?) , you can switch to a simple comment.
Switch to a voting comment New
victory108
5 days, 13 hours ago
Selected Answer: B
B. Perform a sprint risk assessment and analyze challenges
upvoted 1 times
...
517f9da
6 months, 1 week ago
Selected Answer: B
B. Perform a sprint risk assessment and analyze challenges. Explanation: Conducting a sprint risk assessment and analyzing the challenges posed by the new regulation allows the project manager to understand the impact, identify potential solutions, and adjust the project plan accordingly. This proactive approach helps in making informed decisions on how to proceed with the deliverable and ensures compliance with regulatory requirements.
upvoted 1 times
...
odylec
10 months, 4 weeks ago
Selected Answer: B
B is the answer. Considering the urgency and potential impact on the project, option B (Perform a sprint risk assessment and analyze challenges) seems to be a reasonable approach. This would allow the project manager to gather information, assess the risks, and make informed decisions about how to proceed in light of the regulator's ban.
upvoted 1 times
...
Ella008
11 months, 2 weeks ago
b: Perform a risk sprint assessment and analyze challenges
upvoted 1 times
...
Community vote distribution
A (35%)
C (25%)
B (20%)
Other
Most Voted
A voting comment increases the vote count for the chosen answer by one.

Upvoting a comment with a selected answer will also increase the vote count towards that answer by one. So if you see a comment that you already agree with, you can upvote it instead of posting a new comment.

SaveCancel
Loading ...