Welcome to ExamTopics
ExamTopics Logo
- Expert Verified, Online, Free.
exam questions

Exam PMP All Questions

View all questions & answers for the PMP exam

Exam PMP topic 1 question 1124 discussion

Actual exam question from PMI's PMP
Question #: 1124
Topic #: 1
[All PMP Questions]

A project manager has access to risk management tools but chooses to use a quantitative method to evaluate the project risks. During project execution, the project sponsor asks for an updated risk matrix.

What should the project manager do next?

  • A. Use integrated risk management software to evaluate the risks.
  • B. Trust in the quantitative method already chosen as it is a precise method.
  • C. Add new risks and send the risk matrix to leadership for approval.
  • D. Use their own professional knowledge to reassess the risks.
Show Suggested Answer Hide Answer
Suggested Answer: A 🗳️

Comments

Chosen Answer:
This is a voting comment (?) , you can switch to a simple comment.
Switch to a voting comment New
victory108
3 weeks, 3 days ago
Selected Answer: A
A. Use integrated risk management software to evaluate the risks
upvoted 1 times
...
Kim222
2 months, 3 weeks ago
Selected Answer: D
Think simply. The sponsor requests an updated risk matrix, and the PM evaluates it, updates it, and gives the request to the sponsor.
upvoted 1 times
...
Abdelmonm
10 months, 2 weeks ago
Selected Answer: D
The project manager should use their professional knowledge to reassess the risks. While quantitative methods can provide valuable insights, the project manager's expertise and judgment play a crucial role in evaluating risks, especially in responding to specific requests from the project sponsor. The project manager may consider the quantitative data along with other factors to provide a comprehensive and informed update to the risk matrix.
upvoted 1 times
...
kevzzz
10 months, 3 weeks ago
Selected Answer: C
sponsor asks for an updated risk matrix
upvoted 1 times
...
atoms101
11 months, 1 week ago
Selected Answer: C
Because risk matrix is always up to date.
upvoted 1 times
...
Jaya12
11 months, 2 weeks ago
Selected Answer: A
Utilizing integrated risk management software aligns with pre-approved risk assessment methods and tools.
upvoted 2 times
...
gsap
11 months, 2 weeks ago
Selected Answer: C
I think C is more appropriate response as it will ensure that the risk matrix stays current
upvoted 1 times
...
6thEditionAndy
11 months, 2 weeks ago
Selected Answer: A
I think we should use the pre-approved risk assessment methods. An option to argue for a different measurement is missing.
upvoted 3 times
...
Community vote distribution
A (35%)
C (25%)
B (20%)
Other
Most Voted
A voting comment increases the vote count for the chosen answer by one.

Upvoting a comment with a selected answer will also increase the vote count towards that answer by one. So if you see a comment that you already agree with, you can upvote it instead of posting a new comment.

SaveCancel
Loading ...