At a project status meeting, different activities were agreed upon for the following weeks. At the end of the first week. the project team realizes that the activities were executed in the wrong way because each team member had a different understanding. These misunderstandings have caused a delay in the project.
Which of the following actions should the project manager take to avoid this situation in the future?
6thEditionAndy
Highly Voted 9 months, 2 weeks agoKim222
Most Recent 3 weeks, 2 days agoTrytrio
7 months, 3 weeks agoUppersquareCapital
7 months, 3 weeks agoAbdelmonm
8 months, 2 weeks ago