Actual exam question from PMI's PMP
Question #: 1078
Topic #: 1
[All PMP Questions]

A project manager is working on a project that is required to deliver value on an incremental basis. Which action should the project manager take to enable successful project execution?

  • A. Identify the tangible and intangible benefits.
  • B. Create a project schedule containing milestones.
  • C. Engage with the project sponsor to understand the scope.
  • D. Develop a comprehensive set of requirements.
Show Suggested Answer Hide Answer
Suggested Answer: B 🗳️

Comments

Chosen Answer:
This is a voting comment (?) , you can switch to a simple comment.
Switch to a voting comment New
victory108
1 month ago
Selected Answer: B
B. Create a project schedule containing milestones
upvoted 1 times
...
dimo475
8 months, 1 week ago
B because I ll buy from ChatGPT which sais: "In a project that aims to deliver value on an incremental basis, creating a project schedule containing milestones is crucial. Incremental delivery means breaking down the project into smaller, manageable pieces or increments, each of which delivers some tangible value. Milestones mark the completion of these increments or stages and help track progress. By having a well-defined schedule with milestones, the project manager can ensure that the project progresses in a structured manner, meeting the incremental delivery requirements and ultimately achieving success. While options A, C, and D are important actions in project management, they may not directly address the specific need for enabling successful execution of a project with incremental value delivery."
upvoted 2 times
...
[Removed]
8 months, 3 weeks ago
Selected Answer: A
It is about business value. The net quantifiable benefit (tangible and/or intangible) identified from a business endeavor.
upvoted 1 times
...
Trytrio
9 months, 3 weeks ago
Selected Answer: C
C - This approach ensures a clear understanding of the project's scope and objectives, which is crucial for effective incremental delivery. Engaging with the project sponsor helps in aligning the project's execution with the sponsor's expectations and the project's goals, thereby enabling the project manager to plan and manage the incremental delivery more effectively.
upvoted 2 times
...
FZZZN
9 months, 3 weeks ago
Hi admin and all, I just want to know, in most of the questions, the correct answer is marked with green tab and the there are most voted answers. So, as per PMBOK, which answer is exactly correct? green tab or most voted. If green tab is incorrect, then this website EXAMTOPIC is fake. it will make you fail the exam.
upvoted 2 times
...
Davard
10 months ago
Selected Answer: B
This option is aligned with enabling incremental delivery. Creating a project schedule containing milestones allows the project manager to plan and track the delivery of incremental outcomes or increments of value. Milestones mark significant points in the project timeline where specific deliverables or objectives are achieved. By breaking down the project into manageable increments with clear milestones, the project manager can ensure that progress is measurable and aligned with the project's incremental delivery approach.
upvoted 4 times
...
UppersquareCapital
10 months, 1 week ago
Selected Answer: B
Incremental delivery of value often aligns with an iterative or incremental project management approach, such as Agile or Scrum. Creating a project schedule containing milestones allows the project manager to plan and track the incremental delivery of value over time. This helps in breaking down the project into manageable components and ensures that value is delivered regularly throughout the project's lifecycle.
upvoted 3 times
...
Delab202
10 months, 1 week ago
Selected Answer: B
To successfully execute a project that is required to deliver value on an incremental basis, the project manager should: B. Create a project schedule containing milestones. This action is crucial for projects with incremental delivery because it helps in breaking down the project into smaller, manageable parts, each with its own set of deliverables and deadlines. By setting milestones, the project manager can ensure a steady progression towards the final goal, with tangible results being delivered at each stage. This approach aligns well with methodologies like Agile, which focus on iterative and incremental delivery of value.
upvoted 3 times
...
Abdelmonm
10 months, 3 weeks ago
Selected Answer: B
Incremental delivery of value suggests a phased or iterative approach. Creating a project schedule with milestones is crucial to track progress and ensure that incremental goals are met. Milestones serve as checkpoints for the completion of key deliverables and help in monitoring the overall project timeline.
upvoted 1 times
...
xcjxcj
10 months, 3 weeks ago
Selected Answer: A
C is incorrect, sponsor does not study scope, he just approve.
upvoted 1 times
...
Waynelau
11 months, 1 week ago
Selected Answer: C
"incremental basis" means that is a predictive project. The PM should define the clear scope with sponsor.
upvoted 1 times
...
Jaya12
11 months, 2 weeks ago
Selected Answer: A
Understanding the tangible (quantifiable) and intangible (qualitative) benefits allows the project manager to prioritize the delivery of incremental value in a manner that aligns with the project's overarching objectives. This action ensures that each incremental release or delivery contributes to the overall benefits the project aims to achieve, thereby enabling successful project execution within an incremental value delivery framework.
upvoted 3 times
...
wisegik
11 months, 2 weeks ago
C is more correct. The project manager should develop a comprehensive set of requirements to enable successful project execution. This will help ensure that the team has a clear understanding of what is expected of them and what they need to deliver.
upvoted 4 times
...
6thEditionAndy
11 months, 2 weeks ago
Selected Answer: A
A seems more targeted to me as it addresses incremental value delivery
upvoted 1 times
...
Community vote distribution
A (35%)
C (25%)
B (20%)
Other
Most Voted
A voting comment increases the vote count for the chosen answer by one.

Upvoting a comment with a selected answer will also increase the vote count towards that answer by one. So if you see a comment that you already agree with, you can upvote it instead of posting a new comment.

SaveCancel
Loading ...