Welcome to ExamTopics
ExamTopics Logo
- Expert Verified, Online, Free.
exam questions

Exam PMP All Questions

View all questions & answers for the PMP exam

Exam PMP topic 1 question 1061 discussion

Actual exam question from PMI's PMP
Question #: 1061
Topic #: 1
[All PMP Questions]

A project needs to acquire a large volume of electrical supplies on a weekly delivery cycle. There are many suppliers interested in partnering, so the project manager feels confident they can negotiate a good price.

What should the project manager do first in order to ensure the best overall value in the future contract?

  • A. Meet with the project sponsor to learn more about past contracting efforts for electrical supplies.
  • B. Contact each of the potential suppliers to understand their price schedules for the required supplies.
  • C. Identify the policies, procedures, guidelines, and legal parameters that are required in the contract.
  • D. Create a time-based bill of materials containing the supplies that need to be delivered each week.
Show Suggested Answer Hide Answer
Suggested Answer: C 🗳️

Comments

Chosen Answer:
This is a voting comment (?) , you can switch to a simple comment.
Switch to a voting comment New
victory108
1 month ago
Selected Answer: C
C. Identify the policies, procedures, guidelines, and legal parameters that are required in the contract
upvoted 1 times
...
Kim222
2 months, 3 weeks ago
Selected Answer: C
Do C first. And do D. Doing D first is problematic. The problem is to guarantee value, but for example, creating a time-based materials list without understanding the legal regulations is a risk.
upvoted 1 times
...
sidje
6 months ago
Selected Answer: C
Connaître les politiques et procédures internes ainsi que les exigences juridiques permettra au chef de projet de structurer correctement le contrat, de négocier en conformité avec les règles établies, et de protéger les intérêts de l'organisation. Une fois ces paramètres clairement définis, le chef de projet pourra ensuite contacter les fournisseurs potentiels avec une compréhension claire des contraintes et des obligations, ce qui facilitera des négociations plus efficaces et alignées avec les exigences organisationnelles et juridiques.
upvoted 1 times
...
[Removed]
8 months, 3 weeks ago
Selected Answer: D
The question is about to ensure the "best overall value". So the best option for value is D.
upvoted 1 times
...
Trytrio
9 months, 3 weeks ago
Selected Answer: C
Its C - then you would do D
upvoted 1 times
...
Davard
10 months ago
Selected Answer: D
C does not focus on overall value, though of course, understanding policy is a good first step for any project initiation. D seems best here. ChatGPT 3.5 says B, which is okay, but I have since convinced it that D is better. I think having an understanding of the required materials before contacting each supplier would be better than contacting the suppliers blindly.
upvoted 1 times
...
Abdelmonm
10 months, 3 weeks ago
Selected Answer: C
Before engaging with potential suppliers or negotiating prices, the project manager should first identify the policies, procedures, guidelines, and legal parameters that need to be considered in the contract. This involves understanding the regulatory and legal requirements, as well as any specific policies or guidelines that govern the procurement process. By doing so, the project manager can ensure that the future contract not only secures a good price but also aligns with legal and organizational standards, promoting a fair and compliant procurement process. This foundational step sets the groundwork for a successful and value-driven contract negotiation process.
upvoted 4 times
...
atoms101
11 months ago
Selected Answer: C
For future whats you reference , ofcourse policies,procedure and guidelines.
upvoted 2 times
...
Jaya12
11 months, 2 weeks ago
Selected Answer: D
This step lays the groundwork for understanding the specific supplies required, which is essential information when negotiating with potential suppliers to ensure the best overall value in the contract. After this, it's crucial to proceed with actions that encompass price negotiation, supplier evaluation, contract terms, and legal aspects to secure the best possible contract for the project's needs.
upvoted 2 times
...
6thEditionAndy
11 months, 2 weeks ago
Selected Answer: D
I think we need to know the exact volume first, as many companies provide large discounts based on that
upvoted 1 times
...
Community vote distribution
A (35%)
C (25%)
B (20%)
Other
Most Voted
A voting comment increases the vote count for the chosen answer by one.

Upvoting a comment with a selected answer will also increase the vote count towards that answer by one. So if you see a comment that you already agree with, you can upvote it instead of posting a new comment.

SaveCancel
Loading ...