A project manager has been running an agile project for 6 months and has been reporting that the project is on track every week. However, on the last week before releasing the final product, the team found a technical impediment that put the project delivery in jeopardy overnight.
What should the project manager have done to prevent this situation?
victory108
1 month, 1 week agoNgho
1 month, 2 weeks agoKim222
2 months, 3 weeks agoNA1234567
2 months, 3 weeks ago517f9da
6 months, 2 weeks agoTrytrio
9 months, 3 weeks agoUppersquareCapital
10 months, 2 weeks agoAbdelmonm
10 months, 2 weeks agochlaithem
10 months, 2 weeks agoced45c8
10 months, 3 weeks ago6thEditionAndy
11 months, 2 weeks ago