A project manager has been running an agile project for 6 months and has been reporting that the project is on track every week. However, on the last week before releasing the final product, the team found a technical impediment that put the project delivery in jeopardy overnight.

What should the project manager have done to prevent this situation?

  • A. Considered historical data from previous projects with similar impediments to help identify the possible solutions
  • B. Sought and implemented alternative ways to track progress and impediments to identify potential threats
  • C. Provided technical training to the team in advance to ensure the team had high-level technical skills
  • D. Developed a risk response plan that would have provided options and strategies regarding project risk exposure
Show Suggested Answer Hide Answer
Suggested Answer: D 🗳️

Comments

Chosen Answer:
This is a voting comment (?) , you can switch to a simple comment.
Switch to a voting comment New
victory108
1 month, 1 week ago
Selected Answer: D
D. Developed a risk response plan that would have provided options and strategies regarding project risk exposure
upvoted 1 times
...
Ngho
1 month, 2 weeks ago
D. Developed a risk response plan that would have provided options and strategies regarding project risk exposure. In agile projects, it is critical to proactively manage risks by identifying potential threats early and developing response strategies to address them if they materialize. A robust risk response plan would have helped the project manager anticipate technical impediments and have a set of actions or contingencies in place, reducing the likelihood of jeopardizing the project at the last minute. While tracking progress, implementing alternative ways to identify threats, and providing technical training are valuable, the lack of a risk management plan is the key issue in this situation.
upvoted 1 times
...
Kim222
2 months, 3 weeks ago
Selected Answer: D
This is D
upvoted 1 times
...
NA1234567
2 months, 3 weeks ago
Selected Answer: B
risk response is developed for risk which is identified earlier and has a probability of occurrence. Here the problem that popped up is an issue and wasn't identified as risk earlier. So how wud there be a risk response?
upvoted 1 times
...
517f9da
6 months, 2 weeks ago
Selected Answer: D
Oh that sounds so stressful. D. Developed a risk response plan that would have provided options and strategies regarding project risk exposure Explanation: Developing a risk response plan involves identifying potential risks and creating strategies to address them if they occur.
upvoted 1 times
...
Trytrio
9 months, 3 weeks ago
Selected Answer: D
Question is a bit tricky: but threats are covered by the risk response plan. so D should be right
upvoted 2 times
...
UppersquareCapital
10 months, 2 weeks ago
Selected Answer: D
In Agile project management, it's essential to proactively identify, assess, and plan responses to potential risks. Developing a risk response plan allows the project manager and the team to anticipate and address potential issues before they become critical. In this scenario, the project manager should have identified technical impediments as potential risks and developed a risk response plan that outlines strategies for mitigating or addressing these impediments. Option B (Sought and implemented alternative ways to track progress and impediments) is important for monitoring and addressing issues as they arise, but it doesn't replace the need for a comprehensive risk response plan.
upvoted 2 times
...
Abdelmonm
10 months, 2 weeks ago
Selected Answer: D
The project manager should have proactively developed a risk response plan to address potential risks, including technical impediments. A risk response plan outlines how the project team will handle identified risks, including strategies for mitigating, accepting, transferring, or avoiding the risks. By anticipating potential technical challenges and developing a plan to address them, the project manager could have been better prepared to respond quickly and effectively when the impediment arose. This proactive approach aligns with good risk management practices in project management.
upvoted 1 times
...
chlaithem
10 months, 2 weeks ago
Selected Answer: D
answer is D Agile mindset: Agile methodologies emphasize iterative development and continuous risk management. A defined risk response plan, updated throughout the project, would have identified potential technical impediments (option A) and facilitated mitigation strategies. Multiple tracking methods: While solely reporting "on track" is not ideal, relying solely on single progress tracking methods (option B) can miss hidden roadblocks. Diversified tracking measures, including code reviews, technical debt logs, and retrospective discussions, could have highlighted emerging technical issues. Technical training: While broad technical skills (option C) are useful, in most cases, they wouldn't directly predict specific impediments. A risk response plan, however, would outline potential issues and define actions regardless of the team's skill level.
upvoted 1 times
...
ced45c8
10 months, 3 weeks ago
Selected Answer: B
B makes more sense. as the issue happened overnight after project progressing on track for 6 month. Risk plan most probably was defined well that could keeps project on track for 6 month. what happens is like an unknown threat that nobody pays attention to it, before. I guess B is better option
upvoted 2 times
...
6thEditionAndy
11 months, 2 weeks ago
Selected Answer: B
To prevent that the risk was unforeseen, the PM needed a different tracking of project progress and risks. B makes most sense to me
upvoted 4 times
...
Community vote distribution
A (35%)
C (25%)
B (20%)
Other
Most Voted
A voting comment increases the vote count for the chosen answer by one.

Upvoting a comment with a selected answer will also increase the vote count towards that answer by one. So if you see a comment that you already agree with, you can upvote it instead of posting a new comment.

SaveCancel
Loading ...