Welcome to ExamTopics
ExamTopics Logo
- Expert Verified, Online, Free.
exam questions

Exam PMP All Questions

View all questions & answers for the PMP exam

Exam PMP topic 1 question 994 discussion

Actual exam question from PMI's PMP
Question #: 994
Topic #: 1
[All PMP Questions]

During project execution, the client requires several changes that will impact the project's duration. The project manager needs to apply fast-tracking techniques to accelerate the schedule, but the team is concerned about working overtime.

What should the project manager do to motivate the team?

  • A. Negotiate with the client to reduce the changes in requirements.
  • B. Crash the project schedule to ensure completion on time.
  • C. Introduce team-building activities to improve team performance.
  • D. Meet with the team members to review their roles and responsibilities.
Show Suggested Answer Hide Answer
Suggested Answer: C 🗳️

Comments

Chosen Answer:
This is a voting comment (?) , you can switch to a simple comment.
Switch to a voting comment New
6thEditionAndy
Highly Voted 9 months, 2 weeks ago
If I have to work overtime and then my manager says "on top of the overtime, lets do some team building that will consume even more of your time" its time to say bye.
upvoted 11 times
KennyMuffins
7 months ago
While i fully agree with your statement, my answer still has to be C, as that seems to be the most valid for improving team morale. However, will take into consideration of not planning team bonding activities outside of work hours and seek alternatives.
upvoted 1 times
...
...
Kim222
Most Recent 1 month, 2 weeks ago
Selected Answer: C
There is no answer worth debating other than C. I don't think C is a clear answer.
upvoted 1 times
...
517f9da
4 months, 1 week ago
Selected Answer: C
C. Introduce team-building activities to improve team performance. Pretty straight forward
upvoted 1 times
...
PeterCK
5 months, 1 week ago
In real world, C is the thing you should do. Yes, it will take extra time but after took that time. The team performance will be better and work faster. OT may not require anymore.
upvoted 1 times
...
Stopper
6 months ago
Selected Answer: A
Project crashing is when you shorten the duration of a project by reducing the time of one or more tasks. Crashing is done by increasing the resources to the project, which helps make tasks take less time than what they were planned for. Of course, this also adds to the cost of the overall project.
upvoted 1 times
...
Trytrio
7 months, 3 weeks ago
Selected Answer: C
it should be C to boost morale
upvoted 1 times
...
Abdelmonm
7 months, 4 weeks ago
Selected Answer: C
In a situation where the team is concerned about working overtime and motivation is needed, introducing team-building activities can be an effective strategy. Team-building activities can help improve communication, collaboration, and morale within the team. This can create a positive work environment and enhance the team's ability to handle challenges, including the need for accelerated schedules. It's important to address the team's concerns and foster a supportive atmosphere. While negotiating with the client and crashing the schedule are potential actions, they may not directly address the team's motivation and concerns about working overtime.
upvoted 1 times
...
UppersquareCapital
8 months, 1 week ago
Selected Answer: C
Introducing team-building activities can help improve team morale, collaboration, and overall performance. When facing a situation where fast-tracking is necessary, and the team is concerned about working overtime, building a positive and cohesive team environment can contribute to increased motivation and productivity. Option B (Crash the project schedule to ensure completion on time) is a technique to accelerate the schedule, but it doesn't directly address the team's concerns about working overtime. Fast-tracking and crashing should be done carefully, taking into consideration the team's well-being.
upvoted 1 times
...
ced45c8
8 months, 2 weeks ago
Selected Answer: B
team already has concern about overtime team building not only solve the problem but also is extra time on top of working over time. this solution won't satisfy team. the most possible option is B
upvoted 2 times
...
Community vote distribution
A (35%)
C (25%)
B (20%)
Other
Most Voted
A voting comment increases the vote count for the chosen answer by one.

Upvoting a comment with a selected answer will also increase the vote count towards that answer by one. So if you see a comment that you already agree with, you can upvote it instead of posting a new comment.

SaveCancel
Loading ...