During project execution, the client requires several changes that will impact the project's duration. The project manager needs to apply fast-tracking techniques to accelerate the schedule, but the team is concerned about working overtime.
What should the project manager do to motivate the team?
6thEditionAndy
Highly Voted 11 months, 2 weeks agoKennyMuffins
9 months agovictory108
Most Recent 1 month, 1 week agoKim222
3 months, 2 weeks ago517f9da
6 months, 2 weeks agoPeterCK
7 months, 1 week agoStopper
8 months, 1 week agoTrytrio
9 months, 3 weeks agoAbdelmonm
10 months agoUppersquareCapital
10 months, 2 weeks agoced45c8
10 months, 3 weeks ago