Welcome to ExamTopics
ExamTopics Logo
- Expert Verified, Online, Free.
exam questions

Exam PMP All Questions

View all questions & answers for the PMP exam

Exam PMP topic 1 question 973 discussion

Actual exam question from PMI's PMP
Question #: 973
Topic #: 1
[All PMP Questions]

Two project managers are working on separate projects that have identified the same subject matter expert (SME) as critical to their projects. Project A is using a predictive approach and Project B is using an agile approach.

Which project should the SME be allocated to?

  • A. The project with the less experienced project manager to improve the likelihood of success.
  • B. The project with the highest score in the program to improve the likelihood of success.
  • C. Project A, because project planning was based on the assumption that the SME would be available.
  • D. Project B, because success in an agile project is determined by technical excellence.
Show Suggested Answer Hide Answer
Suggested Answer: B 🗳️

Comments

Chosen Answer:
This is a voting comment (?) , you can switch to a simple comment.
Switch to a voting comment New
Ngho
1 month, 2 weeks ago
The project with the highest score in the program to improve the likelihood of success. In this case, the decision should be based on the overall strategic importance and priority of the projects within the program. Allocating the SME to the project that scores the highest in terms of strategic importance, risk, and potential benefits ensures that the organization maximizes its resources to achieve the best possible outcomes. It is not necessarily about the approach (predictive or agile) or the experience level of the project manager, but rather which project will have the greatest impact on the organization's objectives.
upvoted 1 times
...
Kim222
3 months, 2 weeks ago
Why do so many people choose C? Please explain. I don't understand.
upvoted 1 times
...
517f9da
6 months, 2 weeks ago
Selected Answer: C
LOL what score, B is irrelevant. C. Project A, because project planning was based on the assumption that the SME would be available. Allocating the SME to Project A ensures that the project's initial planning assumptions are met, reducing the risk of project delays or failures.
upvoted 1 times
...
UppersquareCapital
10 months, 2 weeks ago
Selected Answer: C
While the other options may have some merit, the key consideration in this case is to avoid disrupting the plan that was made based on the assumption of the SME's availability, which is more typical in predictive project management methodologies. Project A planned its activities assuming the availability of the SME, which is part of the predictive (or traditional) project management approach. Changing critical resources mid-project in predictive environments can lead to disruptions and deviations from the planned schedule. Project B, which is using an agile approach, is more flexible in adapting to changes, and agile projects often prioritize responding to change over following a plan.
upvoted 3 times
...
Abdelmonm
10 months, 2 weeks ago
Selected Answer: C
In a predictive (or traditional) project management approach, planning is done upfront, and dependencies, including critical resources like SMEs, are typically identified early in the project. If Project A's plan assumed the availability of the SME, allocating the SME to Project A aligns with the initial project assumptions and plans. This helps maintain consistency with the project's original baseline and reduces the risk of disruptions caused by changes in resource allocation.
upvoted 1 times
...
Waynelau
10 months, 3 weeks ago
Selected Answer: B
Should be B instead of C. If project A is a ten dollars project and project B is a billion project, which project should be assigned?
upvoted 2 times
...
odylec
11 months ago
Selected Answer: D
D is the answer.
upvoted 1 times
odylec
11 months ago
In agile frameworks, adaptability and continuous delivery are crucial, making the SME's technical expertise invaluable. As Project B follows an agile approach, the SME's contribution can enhance the team's capabilities, addressing technical complexities. Collaboration and cross-functional teamwork in agile settings further support the integration of specialized skills. This decision should be made collaboratively, considering the specific context, project requirements, and ongoing priorities. Ultimately, allocating the SME to Project B can contribute significantly to achieving the technical excellence required for agile project success
upvoted 1 times
...
...
loscoe
11 months, 2 weeks ago
Selected Answer: B
Both projects would have assumed the need for the SME. The only logical choice would B to ensure at the highest valued project gets the their time.
upvoted 3 times
...
6thEditionAndy
11 months, 3 weeks ago
Selected Answer: B
I would argue the project with the highest value will get critical resource.
upvoted 2 times
...
Community vote distribution
A (35%)
C (25%)
B (20%)
Other
Most Voted
A voting comment increases the vote count for the chosen answer by one.

Upvoting a comment with a selected answer will also increase the vote count towards that answer by one. So if you see a comment that you already agree with, you can upvote it instead of posting a new comment.

SaveCancel
Loading ...