Welcome to ExamTopics
ExamTopics Logo
- Expert Verified, Online, Free.
exam questions

Exam PMP All Questions

View all questions & answers for the PMP exam

Exam PMP topic 1 question 935 discussion

Actual exam question from PMI's PMP
Question #: 935
Topic #: 1
[All PMP Questions]

A customer approaches the product owner with a new requirement and asks for a rough estimation to implement it. The outline of the task would be similar to a prior deliverable.

What should the product owner do to properly inform the customer?

  • A. Analyze the current backlog and the backlog refinement to determine a gap for fulfilling the requirement.
  • B. Check the work breakdown structure (WBS) and the cost estimation for the similar requirement and provide an estimate for the new requirement.
  • C. Revisit the user story of the similar requirement, learn about its story points and velocity, and sketch out the time needed for this requirement.
  • D. Refer to the lessons learned register where the experience and effort of former requirements should have been noted.
Show Suggested Answer Hide Answer
Suggested Answer: C 🗳️

Comments

Chosen Answer:
This is a voting comment (?) , you can switch to a simple comment.
Switch to a voting comment New
Kim222
2 weeks, 5 days ago
Selected Answer: C
PO = user story
upvoted 1 times
...
martinx84
2 months ago
Selected Answer: C
Revisit the user story since we have information available of previous deliverable
upvoted 1 times
...
517f9da
4 months, 1 week ago
Selected Answer: C
C. Revisit the user story of the similar requirement, learn about its story points and velocity, and sketch out the time needed for this requirement. Explanation: Revisiting the user story of the similar requirement and using its story points and velocity provides a more accurate estimation for the new requirement, based on the team's prior experience and performance. This approach ensures that the estimate is informed by relevant historical data.
upvoted 1 times
...
odylec
8 months, 3 weeks ago
Selected Answer: C
C is the answer
upvoted 3 times
...
6thEditionAndy
9 months, 2 weeks ago
Selected Answer: C
I am torn between B and C. I suppose as "product Owner" is mentioned, we are in an Agile project. As WBS is more of a predictive tool, we want to chose the answer with the more agile tool, hence the user story and velocity in answer C.
upvoted 4 times
Kim222
4 weeks ago
B is PM or Team players
upvoted 1 times
...
cb4a6c4
9 months ago
Agree, C seems to be the logical answer.
upvoted 1 times
...
...
Community vote distribution
A (35%)
C (25%)
B (20%)
Other
Most Voted
A voting comment increases the vote count for the chosen answer by one.

Upvoting a comment with a selected answer will also increase the vote count towards that answer by one. So if you see a comment that you already agree with, you can upvote it instead of posting a new comment.

SaveCancel
Loading ...