Exam PMP topic 1 question 906 discussion

Actual exam question from PMI's PMP
Question #: 906
Topic #: 1
[All PMP Questions]

A team is about to close a deployment and is waiting to receive critical information from the customer. The customer continues to postpone sending information, which is consequently delaying the deployment.

What should the project manager have done to prevent the delay?

  • A. Delegated the task to the product owner
  • B. Asked the team to use the sample data
  • C. Engaged the sponsor and sought their support
  • D. Received all key information ahead of time
Show Suggested Answer Hide Answer
Suggested Answer: D 🗳️

Comments

Chosen Answer:
This is a voting comment (?) , you can switch to a simple comment.
Switch to a voting comment New
victory108
1 week, 3 days ago
Selected Answer: D
D. Received all key information ahead of time
upvoted 1 times
...
AirJordan
1 month, 2 weeks ago
Proactive Planning: By ensuring all critical information is received well in advance, the project manager can avoid last-minute delays and dependencies on the customer. Risk Mitigation: This approach helps in identifying potential risks early and allows the team to plan contingencies. Smooth Deployment: Having all necessary information beforehand ensures that the deployment process is smooth and uninterrupted. While engaging the sponsor (A) or using sample data (B) might help in managing the current delay, they are more reactive measures. Delegating the task to the product owner © might not necessarily expedite the process if the root cause is the customer’s delay.
upvoted 1 times
...
vidhubalaji
2 months, 1 week ago
Not able to trust the answers given. Because Q#29 & Q#906 are same, but the suggested answers are different in both questions. My answer is D in a practical situation.
upvoted 1 times
...
517f9da
6 months, 1 week ago
Selected Answer: D
D. Received all key information ahead of time Explanation: Ensuring that all key information is received ahead of time would have prevented the delay, as the project manager would have had all necessary data to proceed with the deployment without dependency on the customer's timeline.
upvoted 3 times
...
UppersquareCapital
10 months, 2 weeks ago
Selected Answer: D
To prevent delays in a deployment, it is crucial for the project manager to ensure that all key information is received ahead of time. This includes actively communicating with the customer and establishing clear expectations regarding the necessary information and its timeline. By proactively obtaining all the required information in advance, the project manager can mitigate the risk of delays and ensure a smoother deployment process. While engaging the sponsor (Option C) could be beneficial in some situations, ensuring that key information is received ahead of time is a more direct and proactive measure to prevent delays.
upvoted 1 times
...
Abdelmonm
10 months, 2 weeks ago
Selected Answer: D
To prevent delays in a deployment, the project manager should have taken proactive steps to ensure that all key information from the customer, necessary for the deployment, was received ahead of time. This could involve effective communication with the customer, setting clear expectations, and establishing a timeline for the receipt of critical information.
upvoted 1 times
...
6thEditionAndy
11 months, 2 weeks ago
Selected Answer: C
The questions asks what the PM should have done. Generally speaking, a PM cant do "receive all information upfront". But a PM could have escalated the issue to the sponsor.
upvoted 1 times
cc02995
11 months, 2 weeks ago
project manager have done to prevent the delay, prevent the delay from happening in the first place.
upvoted 2 times
...
...
Community vote distribution
A (35%)
C (25%)
B (20%)
Other
Most Voted
A voting comment increases the vote count for the chosen answer by one.

Upvoting a comment with a selected answer will also increase the vote count towards that answer by one. So if you see a comment that you already agree with, you can upvote it instead of posting a new comment.

SaveCancel
Loading ...