Question #: 37
Topic #: 1
[All PMI-PBA Questions]

A business analyst has been assigned to a project to implement a new phone system for a customer call center. The business analyst will need to create a business case.
Which of the following components will the business analyst use as input to the business case?

  • A. Product scope
  • B. Work breakdown structure
  • C. Project timeline
  • D. Project scope
Show Suggested Answer Hide Answer
Suggested Answer: D 🗳️

Comments

Chosen Answer:
This is a voting comment (?). It is better to Upvote an existing comment if you don't have anything to add.
Switch to a voting comment New
Ecomexpert
1 week, 3 days ago
Selected Answer: A
Its product scope since it defines features of what business needs
upvoted 1 times
...
AKB968
1 month, 3 weeks ago
Selected Answer: C
C is correct answer, remaining other choices are done in planning such as project scope, product scope and WBS.
upvoted 1 times
...
BonezPL
6 months, 3 weeks ago
definitely A
upvoted 2 times
...
Daphne0411
10 months ago
Should be A
upvoted 3 times
...
Community vote distribution
A (35%)
C (25%)
B (20%)
Other
Most Voted
A voting comment increases the vote count for the chosen answer by one.

Upvoting a comment with a selected answer will also increase the vote count towards that answer by one. So if you see a comment that you already agree with, you can upvote it instead of posting a new comment.

SaveCancel
Loading ...
exam
Someone Bought Contributor Access for:
SY0-701
London, 1 minute ago