Welcome to ExamTopics
ExamTopics Logo
- Expert Verified, Online, Free.
exam questions

Exam PMP All Questions

View all questions & answers for the PMP exam

Exam PMP topic 1 question 1055 discussion

Actual exam question from PMI's PMP
Question #: 1055
Topic #: 1
[All PMP Questions]

A project manager has recently been asked to take over an existing project. The project manager would like to determine how the project has been progressing by tracking features that are in progress. completed. or scheduled to be worked on.

Which of the following can help the project manager assess the state of the project?

  • A. Cumulative flow diagram
  • B. Burndown chart
  • C. Pareto diagram
  • D. Burnup chart
Show Suggested Answer Hide Answer
Suggested Answer: A 🗳️

Comments

Chosen Answer:
This is a voting comment (?) , you can switch to a simple comment.
Switch to a voting comment New
9RedFox_JB
2 weeks, 4 days ago
Selected Answer: A
best example is in PMBOOK 6 880 page. figure 5-7
upvoted 1 times
...
c8ee0e6
2 months, 1 week ago
Selected Answer: A
A cumulative flow diagram (CFD) is a graphical representation of the project's workflow, showing the number of tasks or features in different stages (e.g., in progress, completed, scheduled) over time. This diagram helps the project manager visualize the project's progress, identify bottlenecks, and track the flow of work through various stages. In this scenario, the CFD can help the project manager assess the state of the project by: - Showing the number of features in progress, completed, or scheduled - Identifying any bottlenecks or delays in the workflow - Visualizing the project's progress over time
upvoted 1 times
...
Delab202
8 months, 1 week ago
Selected Answer: A
CFDs visualize the flow of work through different stages B. Burndown charts: Focus on tracking remaining work, not visualizing the flow of features through different stages. C. Pareto diagrams: Identify the most common causes of issues, not track feature progress. D. Burnup charts: Show completed work and scope, but don't visualize the flow through stages.
upvoted 1 times
...
Abdelmonm
8 months, 2 weeks ago
Selected Answer: A
A Cumulative Flow Diagram (CFD) is a visual representation of the flow of work items through different stages of a process. It provides a snapshot of the project's progress by illustrating the status of work items over time. In the context of tracking features in progress, completed, or scheduled, a Cumulative Flow Diagram can show the distribution of features across various stages, helping the project manager assess the state of the project and identify any bottlenecks or areas that need attention.
upvoted 1 times
Abdelmonm
7 months, 3 weeks ago
B. Burndown Chart: a graphical representation of the work completed versus the time elapsed. It typically shows the total work planned for a sprint or project and how much work remains. C. Pareto Diagram: a bar chart that arranges data in descending order of frequency or impact. It helps identify the major factors contributing to a problem by showing the cumulative effect of various issues. Use: It is often used in quality management to prioritize issues, focus improvement efforts on the most significant factors, and achieve the greatest impact with limited resources. D. Burnup Chart: a graphical representation of the work completed versus time, similar to a Burndown Chart. However, a Burnup Chart also includes the total scope of work, showing both completed and planned work.
upvoted 1 times
...
...
cb4a6c4
9 months, 1 week ago
Confused. Burnup chart also tracks the same. Can some one explain which is the best option here!!
upvoted 1 times
Jaya12
9 months, 1 week ago
The key here is they're specifically asking for task status in progress. completed. or scheduled, the cumulative flow diagram would specifically provide the insight required to assess the state of the project. Where as the burndown chart is for tracking work completed and remaining in a specific time frame, like a sprint in Agile methodologies.
upvoted 1 times
...
...
Ella008
9 months, 2 weeks ago
A. Cumulative flow diagram
upvoted 1 times
...
cb4a6c4
9 months, 3 weeks ago
Selected Answer: C
If you compare between Burned Down Chart and Cumulative flow diagram, then cumulative flow diagram would be the choice. Burned down chart only show the work completed and planed for the iteration.
upvoted 1 times
...
Community vote distribution
A (35%)
C (25%)
B (20%)
Other
Most Voted
A voting comment increases the vote count for the chosen answer by one.

Upvoting a comment with a selected answer will also increase the vote count towards that answer by one. So if you see a comment that you already agree with, you can upvote it instead of posting a new comment.

SaveCancel
Loading ...