A project manager has recently been asked to take over an existing project. The project manager would like to determine how the project has been progressing by tracking features that are in progress. completed. or scheduled to be worked on.
Which of the following can help the project manager assess the state of the project?
9RedFox_JB
2 weeks, 4 days agoc8ee0e6
2 months, 1 week agoDelab202
8 months, 1 week agoAbdelmonm
8 months, 2 weeks agoAbdelmonm
7 months, 3 weeks agocb4a6c4
9 months, 1 week agoJaya12
9 months, 1 week agoElla008
9 months, 2 weeks agocb4a6c4
9 months, 3 weeks ago