Exam PMP topic 1 question 1011 discussion

Actual exam question from PMI's PMP
Question #: 1011
Topic #: 1
[All PMP Questions]

A project manager is working on a project to scale an operation globally. This endeavor required multiple interviews with various stakeholders. During the user story creation phase, the product owner met with multiple stakeholders who had different opinions about the requirements.

How should the project manager address this situation?

  • A. Ask the product owner to create the backlog.
  • B. Use a voting system for stakeholders.
  • C. Perform a stakeholder identification analysis.
  • D. Limit the participation from stakeholders.
Show Suggested Answer Hide Answer
Suggested Answer: B 🗳️

Comments

Chosen Answer:
This is a voting comment (?) , you can switch to a simple comment.
Switch to a voting comment New
victory108
1 month, 1 week ago
Selected Answer: C
C. Perform a stakeholder identification analysis
upvoted 1 times
...
Kim222
2 months, 3 weeks ago
Selected Answer: C
This is C
upvoted 2 times
...
Schwery
3 months, 2 weeks ago
Selected Answer: C
from GPT: C. Perform a stakeholder identification analysis. Why: Identify Key Stakeholders: Stakeholder identification analysis helps in understanding who the key stakeholders are, their influence, and their interest in the project. By knowing this, the project manager and product owner can prioritize whose opinions and requirements are most critical to the project's success. Here is why the other options are less preferable: B. Use a voting system for stakeholders: This might help in making decisions quickly, but it could also oversimplify complex issues and overlook the nuanced needs of key stakeholders.
upvoted 2 times
...
LongNH2904
5 months, 1 week ago
Selected Answer: C
According to PMI-PMP, when the product owner meets with multiple stakeholders who have different opinions about the requirements during the user story creation phase, the project manager should take the following action: C. Perform a stakeholder identification analysis. Performing a stakeholder identification analysis will help the project manager to identify the stakeholders who have conflicting requirements and prioritize their needs. This will help the project manager to create a plan to address the conflicting requirements and ensure that all stakeholders are satisfied with the final product. Asking the product owner to create the backlog may not be effective in resolving the conflicting requirements, using a voting system may not be appropriate in this situation, and limiting the participation from stakeholders may not be feasible or desirable.
upvoted 2 times
...
517f9da
6 months, 2 weeks ago
Selected Answer: B
B. Use a voting system for stakeholders Using a voting system for stakeholders helps to prioritize and reach a consensus on the requirements by allowing stakeholders to express their preferences and collectively decide on the most critical user stories.
upvoted 1 times
...
kevzzz
8 months, 2 weeks ago
Selected Answer: C
There is this preconceived notion that authoring user stories is confined to the requirements gathering phase. In fact, user stories post a critical role in communication between stakeholders and development teams throughout the development lifecycle. Stakeholder needs and concerns may change over time, so it’s important to be flexible and adapt the stakeholder engagement plan as required. Regularly monitor and evaluate engagement to make sure that stakeholders are satisfied, with their needs being addressed.
upvoted 2 times
...
Abdelmonm
10 months ago
Selected Answer: B
B. Use a voting system for stakeholders. In situations where multiple stakeholders have different opinions about requirements, using a voting system can help facilitate decision-making and prioritize user stories. This approach involves allowing stakeholders to express their preferences through a voting process, which can be based on factors such as importance, urgency, or alignment with strategic objectives. Using a voting system helps to gather input from various stakeholders, acknowledges their perspectives, and provides a structured way to prioritize user stories. It can contribute to consensus-building and ensure that the most critical or valuable requirements are given priority in the backlog. This approach fosters collaboration and transparency in the decision-making process, enabling the project team to move forward with a clearer understanding of stakeholder priorities.
upvoted 1 times
...
58e5964
10 months ago
Selected Answer: B
If you are talking with stakeholders, a stake holder analysis should have already been done. So if there are differing opinions, then B should be the most appropriate answer, where you enable voting to faciliate decision making, which is what this question is about.
upvoted 1 times
...
mesacgon
10 months, 2 weeks ago
Concuerdo con C, la votación es más utilizada para estimar las historias de usuario y eso lo realiza el equipo del proyecto y no los interesados.
upvoted 2 times
...
Abdelmonm
10 months, 2 weeks ago
Selected Answer: C
In a situation where multiple stakeholders have different opinions about requirements, it's essential to perform a stakeholder identification analysis. This involves identifying and analyzing the interests, influence, and expectations of various stakeholders. By understanding the perspectives of different stakeholders, the project manager can facilitate collaboration and communication, helping to reconcile conflicting opinions and ensure that the user stories adequately capture the diverse requirements. Stakeholder analysis is a valuable tool to manage stakeholder expectations and create a shared understanding of project goals and priorities.
upvoted 2 times
...
chlaithem
10 months, 2 weeks ago
Selected Answer: C
C. Performing a stakeholder identification analysis (recommended): This helps categorize stakeholders based on their power, interest, and impact on the project. It allows the project manager to understand conflicting views within different stakeholder groups and prioritize engagement accordingly
upvoted 2 times
...
Waynelau
11 months, 1 week ago
Selected Answer: B
The answer should be "B". Product owner is creating user stories, the stakeholders should be identified already.
upvoted 1 times
...
Jaya12
11 months, 3 weeks ago
Selected Answer: B
use a voting system for stakeholders to facilitate decision-making and prioritize requirements during the user story creation phase
upvoted 4 times
...
sblivia
11 months, 3 weeks ago
Selected Answer: B
Should be B. If we are in the "user story creation phase", stakeholders are already been identified.
upvoted 4 times
...
cb4a6c4
11 months, 3 weeks ago
Selected Answer: B
Question says - product owner met with the stakeholders but they have different opinion. Then it should be B - Voting!!
upvoted 4 times
...
Community vote distribution
A (35%)
C (25%)
B (20%)
Other
Most Voted
A voting comment increases the vote count for the chosen answer by one.

Upvoting a comment with a selected answer will also increase the vote count towards that answer by one. So if you see a comment that you already agree with, you can upvote it instead of posting a new comment.

SaveCancel
Loading ...