At a daily standup on the second day of the sprint, the product owner asks one of the developers to add more functionality to a product backlog item that was committed to in the sprint planning. The product owner explains that the change is based on a discussion they had with a user, is critical, and should be delivered in the next release.
What should the project manager do?
victory108
1 month, 1 week agoKim222
3 months, 2 weeks agoKim222
2 months, 3 weeks ago517f9da
6 months, 2 weeks agokevzzz
8 months, 2 weeks agoCommonNickname
9 months, 1 week agovrj021819
9 months, 1 week agohoomz
9 months, 1 week agoTrytrio
9 months, 3 weeks ago58e5964
10 months, 1 week agoAbdelmonm
10 months, 2 weeks agochlaithem
10 months, 2 weeks agoAntoFE
10 months, 4 weeks agoamali999
11 months, 1 week agoWaynelau
11 months, 1 week ago6thEditionAndy
11 months, 2 weeks agoJaya12
11 months, 3 weeks agosblivia
11 months, 3 weeks ago