At a daily standup on the second day of the sprint, the product owner asks one of the developers to add more functionality to a product backlog item that was committed to in the sprint planning. The product owner explains that the change is based on a discussion they had with a user, is critical, and should be delivered in the next release.
What should the project manager do?
Kim222
1 month, 1 week agoKim222
2 weeks, 5 days ago517f9da
4 months, 1 week agokevzzz
6 months, 2 weeks agoCommonNickname
7 months agovrj021819
7 months agohoomz
7 months agoTrytrio
7 months, 3 weeks ago58e5964
8 months agoAbdelmonm
8 months, 2 weeks agochlaithem
8 months, 2 weeks agoAntoFE
8 months, 3 weeks agoamali999
9 months agoWaynelau
9 months, 1 week ago6thEditionAndy
9 months, 2 weeks agoJaya12
9 months, 2 weeks agosblivia
9 months, 3 weeks agocb4a6c4
9 months, 3 weeks ago