Exam PMP topic 1 question 1001 discussion

Actual exam question from PMI's PMP
Question #: 1001
Topic #: 1
[All PMP Questions]

A project sponsor is promoting the use of a new technology that has not yet been approved. The technology guarantees cost savings and a delivery ahead of schedule. However, the operational support at project completion is uncertain as the service organization expressed an inability to provide support without approval of the new technology.

What should the project manager do to resolve the conflict?

  • A. Seek to understand the project stakeholders’ needs in an effort to support the new technology.
  • B. Communicate the project’s progress to the stakeholders and promote the new technology.
  • C. Maintain and adhere to project plans to ensure the project delivers successful outcomes.
  • D. Acknowledge the lack of approval and focus on a resolution that will benefit the customer.
Show Suggested Answer Hide Answer
Suggested Answer: D 🗳️

Comments

Chosen Answer:
This is a voting comment (?) , you can switch to a simple comment.
Switch to a voting comment New
victory108
1 month, 1 week ago
Selected Answer: D
D. Acknowledge the lack of approval and focus on a resolution that will benefit the customer
upvoted 1 times
...
sidje
6 months ago
Selected Answer: D
Cette option aborde directement le problème de l'absence d'approbation et de soutien opérationnel, et vise à trouver une solution bénéfique pour le client. Le chef de projet doit travailler à obtenir l'approbation nécessaire ou explorer des alternatives qui garantissent le soutien et la satisfaction du client. Conclusion : Le chef de projet doit reconnaître le manque d'approbation et se concentrer sur une résolution qui profitera au client. Cela peut impliquer de négocier avec l'organisme de service pour obtenir l'approbation de la nouvelle technologie ou de trouver une technologie alternative déjà approuvée.
upvoted 1 times
...
vrj021819
9 months, 1 week ago
D, analyse the impact and bring in a solution
upvoted 1 times
...
Abdelmonm
10 months, 2 weeks ago
Selected Answer: D
n this situation, it's important for the project manager to acknowledge the uncertainty and lack of approval for the new technology. The project manager should then work towards finding a resolution that benefits the customer and aligns with the overall project goals. This may involve collaborating with stakeholders, including the service organization, to address concerns and seek alternative solutions that ensure the project's success and address operational support considerations. Effective communication and collaboration are key in resolving conflicts and navigating uncertainties in project management.
upvoted 1 times
...
chlaithem
10 months, 2 weeks ago
Selected Answer: D
D. Acknowledge the lack of approval and focus on a resolution that will benefit the customer. Here's why: Unapproved technology: Promoting a technology without proper approval (option B) creates unnecessary risks and can lead to project delays or complications if support isn't available later. Stakeholder understanding (option A) and project plans (option C): While understanding stakeholder needs and adhering to plans are important, they must be aligned with project feasibility and compliance. Using an unapproved technology might conflict with existing plans and raise concerns. Customer interest: By prioritizing a customer-beneficial resolution (option D), the project manager can advocate for a solution that addresses both cost savings and potential support issues.
upvoted 1 times
...
cb4a6c4
11 months, 3 weeks ago
Selected Answer: D
Resolve the Conflict - Its D
upvoted 1 times
...
Community vote distribution
A (35%)
C (25%)
B (20%)
Other
Most Voted
A voting comment increases the vote count for the chosen answer by one.

Upvoting a comment with a selected answer will also increase the vote count towards that answer by one. So if you see a comment that you already agree with, you can upvote it instead of posting a new comment.