A project sponsor has requested that the project manager reprioritize the team's tasks to include a feature that is not part of the minimum viable product (MVP) for the project. Although the project sponsor is very keen on the feature, adding it has the potential of causing team burnout and/or delaying the release.
How should the project manager address this situation?
Kim222
2 weeks, 5 days agoKim222
1 month, 1 week agoKim222
2 weeks, 5 days ago517f9da
4 months, 1 week agohoomz
7 months agoTrytrio
7 months, 3 weeks agoUppersquareCapital
8 months, 1 week agoced45c8
8 months, 2 weeks agoamali999
9 months ago6thEditionAndy
9 months, 2 weeks agoJaya12
9 months, 2 weeks agocb4a6c4
9 months, 3 weeks ago