A project sponsor has requested that the project manager reprioritize the team's tasks to include a feature that is not part of the minimum viable product (MVP) for the project. Although the project sponsor is very keen on the feature, adding it has the potential of causing team burnout and/or delaying the release.
How should the project manager address this situation?
victory108
1 month agoKim222
3 months, 3 weeks agoKim222
4 months, 2 weeks agoKim222
3 months, 3 weeks ago517f9da
7 months, 2 weeks agohoomz
10 months, 1 week agoTrytrio
10 months, 4 weeks agoUppersquareCapital
11 months, 2 weeks agoced45c8
11 months, 3 weeks agoamali999
1 year ago6thEditionAndy
1 year agoJaya12
1 year agocb4a6c4
1 year ago