Welcome to ExamTopics
ExamTopics Logo
- Expert Verified, Online, Free.
exam questions

Exam PMP All Questions

View all questions & answers for the PMP exam

Exam PMP topic 1 question 990 discussion

Actual exam question from PMI's PMP
Question #: 990
Topic #: 1
[All PMP Questions]

A project sponsor has requested that the project manager reprioritize the team's tasks to include a feature that is not part of the minimum viable product (MVP) for the project. Although the project sponsor is very keen on the feature, adding it has the potential of causing team burnout and/or delaying the release.

How should the project manager address this situation?

  • A. Ensure the feature has been included in the product backlog, explain to the sponsor the consequences of the request, and ask the team to include the feature's tasks in the next iteration
  • B. Ensure the feature is included in the iteration backlog, ask the team lo work on the current tasks first, and include the new tasks after those tasks are completed
  • C. Ensure the feature has been included in the product backlog, then hold a meeting with the team and sponsor to determine how to deliver the feature within the current iteration
  • D. Ensure the feature’s tasks are included in the iteration backlog. explain to the sponsor the consequences of the request. and ask the team to deliver the feature in the current iteration
Show Suggested Answer Hide Answer
Suggested Answer: A 🗳️

Comments

Chosen Answer:
This is a voting comment (?) , you can switch to a simple comment.
Switch to a voting comment New
Kim222
2 weeks, 5 days ago
Selected Answer: A
This is A. The current sprint iteration cannot be changed.
upvoted 1 times
...
Kim222
1 month, 1 week ago
Selected Answer: C
The answer is C. A is wrong because it is done in the next iteration. It must be placed considering priority within the current repetitive task.
upvoted 1 times
Kim222
2 weeks, 5 days ago
Its A. Sorry
upvoted 1 times
...
...
517f9da
4 months, 1 week ago
Selected Answer: A
A Explanation: Including the feature in the product backlog ensures it is documented and prioritized for future consideration. Explaining the consequences to the sponsor provides transparency about the potential impact on the project. Including the feature in the next iteration avoids immediate burnout and delays, balancing the sponsor's request with the team's capacity. "C" is incorrect because it may pressure the team to fit the feature into the current iteration, increasing the risk of burnout and delays. This isn't very reasonable.
upvoted 1 times
...
hoomz
7 months ago
Selected Answer: A
it is recognized as a potential future enhancement without immediately disrupting the current iteration's work or the MVP's scope.
upvoted 1 times
...
Trytrio
7 months, 3 weeks ago
Selected Answer: A
Would go with A since it is not mentioned how many iterations are still there until release. So the work can potentially wait until the next iteration. Doesnt make sense to change the scope now.
upvoted 2 times
...
UppersquareCapital
8 months, 1 week ago
Selected Answer: C
In Agile project management, it's essential to maintain transparency and collaboration among the team, the product owner (which may include the project sponsor), and other stakeholders. In this situation, the project manager should ensure that the feature is included in the product backlog. However, scheduling the tasks for the current iteration needs to be a collaborative decision. Option C suggests holding a meeting with the team and sponsor to discuss how to deliver the feature within the current iteration. This approach allows for open communication and collaboration, ensuring that everyone is aware of the potential consequences, such as team burnout or release delays. It also provides an opportunity to explore possible solutions or compromises.
upvoted 3 times
...
ced45c8
8 months, 2 weeks ago
Selected Answer: A
the feature is not a part of MVP, so it is not necessary to be considered in the current iteration; that's why C is not valid.
upvoted 2 times
...
amali999
9 months ago
Selected Answer: A
just follow the agile process..add to product backlog...repriorities...add in next iteration...
upvoted 2 times
...
6thEditionAndy
9 months, 2 weeks ago
Selected Answer: C
We have to review the impact this additional work we have with the Sponsor and the team to find an approriate solution. ChatGPTs answer of A is wrong here.
upvoted 2 times
...
Jaya12
9 months, 2 weeks ago
Selected Answer: A
This approach aligns with agile principles and project management practices by ensuring that the requested feature is captured in the product backlog for future consideration. It also involves communication with the sponsor regarding the potential impacts, such as team burnout or project delays, resulting from the immediate inclusion of the feature.
upvoted 1 times
...
cb4a6c4
9 months, 3 weeks ago
Selected Answer: C
Its C: Discuss with the Sponsor and the team....
upvoted 3 times
...
Community vote distribution
A (35%)
C (25%)
B (20%)
Other
Most Voted
A voting comment increases the vote count for the chosen answer by one.

Upvoting a comment with a selected answer will also increase the vote count towards that answer by one. So if you see a comment that you already agree with, you can upvote it instead of posting a new comment.

SaveCancel
Loading ...