Welcome to ExamTopics
ExamTopics Logo
- Expert Verified, Online, Free.
exam questions

Exam PMP All Questions

View all questions & answers for the PMP exam

Exam PMP topic 1 question 1123 discussion

Actual exam question from PMI's PMP
Question #: 1123
Topic #: 1
[All PMP Questions]

A project team is in the planning stage and has prepared a list of activities and completed sequencing the activities. During a review, the team noted that there is a dependency missing between:

• Test the product
• Release to customer

According to the quality management plan, the product must be tested before being released.

How should the project manager enter this dependency?

  • A. Start to start
  • B. Finish to start
  • C. Finish to finish
  • D. Start to finish
Show Suggested Answer Hide Answer
Suggested Answer: B 🗳️

Comments

Chosen Answer:
This is a voting comment (?) , you can switch to a simple comment.
Switch to a voting comment New
victory108
3 weeks, 3 days ago
Selected Answer: B
B. Finish to start
upvoted 1 times
...
Delab202
10 months, 2 weeks ago
Selected Answer: B
The correct way to enter this dependency is B. Finish to start. This is because the "Test the product" activity must be finished before the "Release to customer" activity can start. In a Finish to Start dependency, the initiation of the successor (in this case, releasing the product to the customer) is dependent on the completion of the predecessor (testing the product). This type of dependency is very common in project management, especially in cases where a certain phase or component of the project must be completed before the next phase can commence.
upvoted 2 times
...
kevzzz
10 months, 3 weeks ago
Selected Answer: B
The Finish-to-Start relationship means that one activity — the predecessor — must be fully complete before any following — successor — activities may begin. An example, you must "Finish" testing before you 'Start' the next "Hand Over".
upvoted 1 times
...
Community vote distribution
A (35%)
C (25%)
B (20%)
Other
Most Voted
A voting comment increases the vote count for the chosen answer by one.

Upvoting a comment with a selected answer will also increase the vote count towards that answer by one. So if you see a comment that you already agree with, you can upvote it instead of posting a new comment.

SaveCancel
Loading ...