A project manager finds a mistake with an important server acquisition. The acquisition was expected for a critical path activity but has not arrived yet, causing significant impacts on time and cost. The team member responsible for this activity argues that they sent several emails to the supplier but received no reply.
Which document should be used to help avoid this kind of situation?
sidje
4 months, 1 week agoompk
4 months, 2 weeks agoKim222
1 month, 1 week agoiuedeme
6 months agoYUCHAN2022
7 months, 2 weeks agoTrytrio
7 months, 3 weeks agoAbdelmonm
8 months, 1 week agoDelab202
8 months, 1 week agoDelab202
8 months, 1 week agokevzzz
8 months, 3 weeks agopsvexam
9 months agoxcjxcj
8 months, 1 week agoDivya_Naidu
9 months, 1 week agoJaya12
9 months, 1 week ago6thEditionAndy
9 months, 2 weeks agonewnewuser
9 months, 3 weeks ago