A project manager finds a mistake with an important server acquisition. The acquisition was expected for a critical path activity but has not arrived yet, causing significant impacts on time and cost. The team member responsible for this activity argues that they sent several emails to the supplier but received no reply.
Which document should be used to help avoid this kind of situation?
victory108
3 weeks, 4 days agosidje
6 months, 1 week agoompk
6 months, 2 weeks agoKim222
3 months, 2 weeks agoiuedeme
8 months agoYUCHAN2022
9 months, 2 weeks agoTrytrio
9 months, 3 weeks agoAbdelmonm
10 months, 1 week agoDelab202
10 months, 2 weeks agoDelab202
10 months, 2 weeks agokevzzz
10 months, 3 weeks agopsvexam
11 months agoxcjxcj
10 months, 1 week agoDivya_Naidu
11 months, 1 week agoJaya12
11 months, 2 weeks ago6thEditionAndy
11 months, 2 weeks agonewnewuser
11 months, 3 weeks ago