A project manager is newly assigned to the second phase of an ongoing project. During the implementation, a defect occurred and no one knows how to fix it, as the former engineering team has moved to another project. The customer warns that previously. this defect negatively affected the project schedule.
What should the project manager do first?
victory108
3 weeks, 6 days agodimo475
8 months, 1 week ago125bb38
9 months, 3 weeks agoTrytrio
9 months, 3 weeks agoDelab202
10 months, 2 weeks agoAbdelmonm
10 months, 2 weeks agopsvexam
11 months agokevzzz
11 months, 2 weeks agonewnewuser
11 months, 3 weeks ago