A risk was raised during the initiation of a project. The supplier discontinued software support for one of the project’s required inputs. The project manager planned a reserve budget to allow the project to continue in the event of this occurrence.
What should the project manager do?
victory108
1 month, 1 week agoPmpjune152024
5 months, 2 weeks agoTrytrio
9 months, 3 weeks agoFarnoudamir
9 months, 3 weeks agomesacgon
10 months, 1 week agoUppersquareCapital
10 months, 1 week agoAbdelmonm
10 months, 3 weeks agopsvexam
11 months agocb4a6c4
11 months, 3 weeks agonewnewuser
11 months, 4 weeks ago