Question #: 903
Topic #: 1
[All PMP Questions]

A project manager is assigned to a critical project to build a complex application for a client whose goal is to achieve an ideal state for their business model, but is unsure about how to achieve the solution. What collaboration model should the project manager recommend in this situation?

  • A. Ask the client to specify their business needs in a contract format and approve it.
  • B. Schedule quarterly review meetings with the client.
  • C. Request that proper stakeholders, including the client, are assigned.
  • D. Ask the project team to write the business requirements based on the client's needs.
Show Suggested Answer Hide Answer
Suggested Answer: C 🗳️

Comments

Chosen Answer:
This is a voting comment (?) , you can switch to a simple comment.
Switch to a voting comment New
victory108
1 week, 3 days ago
Selected Answer: C
C. Request that proper stakeholders, including the client, are assigned
upvoted 1 times
...
517f9da
6 months, 1 week ago
Selected Answer: C
C. Request that proper stakeholders, including the client, are assigned. Explanation: Ensuring that proper stakeholders, including the client, are involved in the project facilitates ongoing collaboration and communication, which is essential for achieving the client's goals and developing the best solution.
upvoted 1 times
...
xcjxcj
10 months, 1 week ago
Selected Answer: D
D. Ask the project team to write the business requirements based on the client's needs
upvoted 1 times
...
UppersquareCapital
10 months, 2 weeks ago
Selected Answer: C
C. Request that proper stakeholders, including the client, are assigned. In a situation where the client has a goal but is unsure about how to achieve the solution, a collaborative and iterative approach is often more effective. Requesting that proper stakeholders, including the client, are assigned is aligned with the principles of collaboration and ensures that the right people are actively involved in the project. This approach supports ongoing communication, feedback, and the ability to adapt the project as the client gains clarity on their requirements and goals.
upvoted 1 times
...
Abdelmonm
10 months, 2 weeks ago
Selected Answer: C
In a situation where the client has a goal but is unsure about how to achieve the solution, a collaborative approach involving the client and relevant stakeholders is crucial. This ensures active and continuous involvement of those who have a vested interest in the project's success. Option C, "Request that proper stakeholders, including the client, are assigned," aligns with a collaborative model where key stakeholders, including the client, actively participate in the project.
upvoted 1 times
...
dapper18
10 months, 3 weeks ago
its d you need requirements
upvoted 1 times
...
cb4a6c4
11 months, 3 weeks ago
Selected Answer: C
C and then the team can look at preparing the document.
upvoted 2 times
...
cb4a6c4
11 months, 3 weeks ago
Selected Answer: D
Shouldn't it be D?
upvoted 1 times
...
Community vote distribution
A (35%)
C (25%)
B (20%)
Other
Most Voted
A voting comment increases the vote count for the chosen answer by one.

Upvoting a comment with a selected answer will also increase the vote count towards that answer by one. So if you see a comment that you already agree with, you can upvote it instead of posting a new comment.

SaveCancel
Loading ...