Question #: 998
Topic #: 1
[All PMP Questions]

A construction project to build a fish hatchery is in execution. The operations group notified the project manager about a concern that might turn into a potential issue; however, the concern could not be addressed.

In which project document should the project manager record the concern?

  • A. Request for information
  • B. Scope statement
  • C. Risk register
  • D. Issue log
Show Suggested Answer Hide Answer
Suggested Answer: C 🗳️

Comments

Chosen Answer:
This is a voting comment (?) , you can switch to a simple comment.
Switch to a voting comment New
victory108
1 month, 1 week ago
Selected Answer: C
C. Risk register
upvoted 1 times
...
517f9da
6 months, 2 weeks ago
Selected Answer: C
C. Risk register Explanation: The risk register is the appropriate document for recording concerns that might turn into potential issues.
upvoted 1 times
...
Sunshine2022
6 months, 2 weeks ago
Selected Answer: C
Risks are documented in the Risk Register for what could happen. Issues are recorded in the Issue Log for what is or did happen. Risks have a probability of occurrence rating; issues do not because they did happen or are occurring.
upvoted 1 times
...
Trytrio
9 months, 3 weeks ago
Selected Answer: C
Recording the concern in the Risk Register (Option C) is indeed a valid approach in this context. The Risk Register is used to document and track potential risks that might impact the project. In this case, the concern raised by the operations group about the fish hatchery construction, although not yet a realized issue, represents a potential risk to the project and should be documented for proactive management. This allows for risk assessment, planning of mitigation strategies, and monitoring, which are essential components of effective risk management.
upvoted 2 times
...
6thEditionAndy
11 months, 2 weeks ago
Selected Answer: C
A concern that could become an issue is a risk. As we couldnt address the risk now, we have to add it in the risk log and think of a mitigation strategy.
upvoted 3 times
...
Jaya12
11 months, 3 weeks ago
Selected Answer: D
The concern that could not be immediately addressed but has the potential to become an issue should be documented in the Issue Log.
upvoted 1 times
...
newnewuser
11 months, 4 weeks ago
Select D "since the concern could not be addressed" wouldn't this be an issue now?
upvoted 1 times
cb4a6c4
11 months, 3 weeks ago
Its just a concern, update the risk register - Option C
upvoted 1 times
...
...
Community vote distribution
A (35%)
C (25%)
B (20%)
Other
Most Voted
A voting comment increases the vote count for the chosen answer by one.

Upvoting a comment with a selected answer will also increase the vote count towards that answer by one. So if you see a comment that you already agree with, you can upvote it instead of posting a new comment.

SaveCancel
Loading ...