A project manager is executing a commercial building project. The project manager discovers that the required building permits have not been obtained. Obtaining the permits will delay the project by 1 month and will cost the project US$35,000. The fine associated with continuing to build without the permits is US$1,000 per day.
What should the project manager do first?
cb4a6c4
Highly Voted 11 months, 4 weeks agonicknamesdx
6 months, 2 weeks agoNgho
Most Recent 1 month, 2 weeks agoKim222
3 months, 2 weeks ago517f9da
6 months, 2 weeks agoTrytrio
9 months, 3 weeks agoAbdelmonm
10 months agomesacgon
10 months, 2 weeks agochlaithem
10 months, 2 weeks agoxcjxcj
10 months, 3 weeks agoced45c8
10 months, 3 weeks ago6thEditionAndy
11 months, 3 weeks agoJaya12
11 months, 3 weeks agocertificate988
12 months ago