A project manager is executing a commercial building project. The project manager discovers that the required building permits have not been obtained. Obtaining the permits will delay the project by 1 month and will cost the project US$35,000. The fine associated with continuing to build without the permits is US$1,000 per day.
What should the project manager do first?
cb4a6c4
Highly Voted 1 year agonicknamesdx
7 months, 2 weeks agovictory108
Most Recent 1 month agoNgho
2 months, 3 weeks agoKim222
4 months, 2 weeks ago517f9da
7 months, 2 weeks agoTrytrio
10 months, 4 weeks agoAbdelmonm
11 months agomesacgon
11 months, 2 weeks agochlaithem
11 months, 3 weeks agoxcjxcj
11 months, 3 weeks agoced45c8
11 months, 3 weeks ago6thEditionAndy
1 year agoJaya12
1 year agocertificate988
1 year ago