Welcome to ExamTopics
ExamTopics Logo
- Expert Verified, Online, Free.
exam questions

Exam PMP All Questions

View all questions & answers for the PMP exam

Exam PMP topic 1 question 988 discussion

Actual exam question from PMI's PMP
Question #: 988
Topic #: 1
[All PMP Questions]

A project manager is executing a commercial building project. The project manager discovers that the required building permits have not been obtained. Obtaining the permits will delay the project by 1 month and will cost the project US$35,000. The fine associated with continuing to build without the permits is US$1,000 per day.

What should the project manager do first?

  • A. Continue the project while trying to obtain the permit.
  • B. Update the risk management plan.
  • C. Review lessons learned from previous projects.
  • D. Obtain the permits before continuing the build.
Show Suggested Answer Hide Answer
Suggested Answer: D 🗳️

Comments

Chosen Answer:
This is a voting comment (?) , you can switch to a simple comment.
Switch to a voting comment New
cb4a6c4
Highly Voted 11 months, 4 weeks ago
Selected Answer: B
What should Project Manager do First - Update the Risk Management Plan.
upvoted 5 times
nicknamesdx
6 months, 2 weeks ago
I think it should be risk register not the risk management plan
upvoted 1 times
...
...
Ngho
Most Recent 1 month, 2 weeks ago
D. Obtain the permits before continuing the build. Building without the necessary permits is not only illegal but also introduces significant risk to the project, including potential fines, shutdowns, or legal consequences. Although continuing without the permits might seem like a way to avoid delay, it could lead to far greater issues down the line. Obtaining the permits ensures compliance with regulations and avoids escalating costs and legal challenges.
upvoted 1 times
...
Kim222
3 months, 2 weeks ago
Selected Answer: D
This is a test. In reality, we would calculate the cost, but this is where we have to stop construction.
upvoted 1 times
...
517f9da
6 months, 2 weeks ago
Selected Answer: D
D. Obtain the permits before continuing the build. Explanation: Obtaining the permits ensures compliance with legal and regulatory requirements. Continuing the project without the permits can result in significant fines and potential legal issues, which could ultimately be more costly and damaging to the project.
upvoted 1 times
...
Trytrio
9 months, 3 weeks ago
Selected Answer: D
D - otherwise its a legal and might have further consequences
upvoted 1 times
...
Abdelmonm
10 months ago
Selected Answer: D
In this situation, the project manager should prioritize obtaining the required building permits before continuing with the construction. Failing to do so could lead to legal and financial consequences. Once the permits are obtained, the project manager can proceed with the construction in compliance with regulations. Updating the risk management plan and reviewing lessons learned may be valuable for future projects but do not address the immediate need to obtain the permits.
upvoted 1 times
...
mesacgon
10 months, 2 weeks ago
Respuesta es D pero el la vida real es A
upvoted 1 times
...
chlaithem
10 months, 2 weeks ago
Selected Answer: D
D is the answer Legal and financial risk: Continuing construction without permits exposes the project to significant legal repercussions, including daily fines of $1,000, which could quickly amount to much more than the permit cost. Additionally, the construction might be halted or even forced to be demolished, further disrupting the schedule and incurring even higher costs. Project delay: While obtaining the permits will delay the project for a month, continuing without them increases the risk of a longer overall delay if construction is stopped by authorities. The $35,000 permit cost is a smaller financial risk compared to potential fines and construction stoppages. Responsible project management: Obtaining the necessary permits is a fundamental requirement for construction projects. Continuing without them shows disregard for safety regulations and legal compliance
upvoted 1 times
...
xcjxcj
10 months, 3 weeks ago
Selected Answer: C
The gap between answer A and answer D is one month. A saved 1 month, spent $30k. Whether it worth or not, review lesson learned is a good choice. C is best answer.
upvoted 2 times
...
ced45c8
10 months, 3 weeks ago
Selected Answer: C
it is mentioned obtaining permit will delay 1 month, which means in 1 month the permit can obtained. choosing between $35,000 and $30,000 shouldn't be C?
upvoted 1 times
...
6thEditionAndy
11 months, 3 weeks ago
The real answer is missing. What the Project Manager should do first is escalate the issue to the project sponsor. Then, and only then, a decision should be made on how to continue.
upvoted 1 times
...
Jaya12
11 months, 3 weeks ago
Selected Answer: D
While updating the risk management plan is crucial for long-term risk mitigation and project improvement, the primary concern in the immediate scenario is to avoid the daily fines and legal complications by obtaining the required permits before continuing with the project.
upvoted 1 times
...
certificate988
12 months ago
Selected Answer: D
Building w/o permit would cost 30,000 USD for 30 days as per penatly which is less than cost of waiting. But point to note here is that there is no guarantee that permit will be given at all or may take more time. So, there is a high risk associated with it. And also following rules, it should be good to wait until permit is there. Both ways, PM should wait. So, option D is the answer.
upvoted 2 times
...
Community vote distribution
A (35%)
C (25%)
B (20%)
Other
Most Voted
A voting comment increases the vote count for the chosen answer by one.

Upvoting a comment with a selected answer will also increase the vote count towards that answer by one. So if you see a comment that you already agree with, you can upvote it instead of posting a new comment.

SaveCancel
Loading ...