Welcome to ExamTopics
ExamTopics Logo
- Expert Verified, Online, Free.
exam questions

Exam PMP All Questions

View all questions & answers for the PMP exam

Exam PMP topic 1 question 959 discussion

Actual exam question from PMI's PMP
Question #: 959
Topic #: 1
[All PMP Questions]

A sponsor requires that the established quality standards for the project be met. As a result, the sponsor asks the project manager for stable measures to ensure that the quality is met.

Which three actions should the project manager do? (Choose three.)

  • A. Identify in the iteration planning the acceptance criteria that meet quality standards.
  • B. Identify the acceptance criteria during the retrospective that meet the quality standards.
  • C. Analyze the lessons learned to determine appropriate testing metrics in quality standards.
  • D. Incorporate performance metrics on the verified deliverables according to quality standards.
  • E. Perform a risk analysis to determine the impact of not complying with quality standards.
Show Suggested Answer Hide Answer
Suggested Answer: ACD 🗳️

Comments

Chosen Answer:
This is a voting comment (?) , you can switch to a simple comment.
Switch to a voting comment New
victory108
1 day, 6 hours ago
Selected Answer: ACD
A. Identify in the iteration planning the acceptance criteria that meet quality standards C. Analyze the lessons learned to determine appropriate testing metrics in quality standards. D. Incorporate performance metrics on the verified deliverables according to quality standards
upvoted 1 times
...
ea4e1f8
3 months, 1 week ago
Selected Answer: ACD
Why not E ? Here you go!!!!A risk analysis is typically a reactive measure to identify what could go wrong if quality isn't met, rather than an ongoing measure to ensure quality.
upvoted 1 times
...
517f9da
6 months, 1 week ago
Selected Answer: ADE
C is Irrelevant. Nothing says "similar" "same" or anything related to a project that isn't the one at hand. This is straightforward, don't need to add extra metrics that aren't even in the question. Explanation. A - Setting clear acceptance criteria during iteration planning ensures that quality standards are understood and agreed upon before work begins. D - Incorporating performance metrics helps in tracking and verifying that the deliverables meet the established quality standards throughout the project. E - Conducting a risk analysis helps in understanding the potential consequences of not meeting quality standards, allowing for proactive measures to mitigate these risks.
upvoted 1 times
...
kmsinthesky
6 months, 2 weeks ago
Selected Answer: ACD
E. regardless low and high risk, qaultiy standard should be met.
upvoted 1 times
...
Abdelmonm
9 months, 4 weeks ago
Selected Answer: ACD
A. Identifying acceptance criteria during iteration planning ensures that the team understands and agrees upon the quality standards for the deliverables. C. Analyzing lessons learned helps in identifying effective testing metrics and practices that contribute to meeting quality standards. Learning from previous iterations can inform improvements in the testing process. D. Incorporating performance metrics on verified deliverables aligns with quality standards, providing objective measures of the quality of the project deliverables
upvoted 2 times
...
58e5964
10 months ago
Selected Answer: ACD
The only reason C is not the correct answer is if the 'Lessons Learnt' they are referring is related to the current project and not another similar project. So this question can cause confusion if it was in the exam. If C is not an acceptable answer, then the next logical one is E.
upvoted 2 times
...
janojano
10 months, 3 weeks ago
Selected Answer: ACD
ACD is the right answer.
upvoted 1 times
...
Ella008
11 months, 2 weeks ago
A,C,D- the focus is on getting stable measurements
upvoted 1 times
...
cb4a6c4
11 months, 3 weeks ago
ACD is the right answer.
upvoted 1 times
...
certificate988
11 months, 3 weeks ago
Selected Answer: ACD
E can't be answer as it does risk analysis of impact on not meeting quality standards. Here question is to take stable measures to meet quality. C is good option to define testing metrics. A and D are anyway natural choice.
upvoted 2 times
...
Community vote distribution
A (35%)
C (25%)
B (20%)
Other
Most Voted
A voting comment increases the vote count for the chosen answer by one.

Upvoting a comment with a selected answer will also increase the vote count towards that answer by one. So if you see a comment that you already agree with, you can upvote it instead of posting a new comment.

SaveCancel
Loading ...