A sponsor requires that the established quality standards for the project be met. As a result, the sponsor asks the project manager for stable measures to ensure that the quality is met.
Which three actions should the project manager do? (Choose three.)
ea4e1f8
1 month, 1 week ago517f9da
4 months, 1 week agokmsinthesky
4 months, 2 weeks agoAbdelmonm
7 months, 4 weeks ago58e5964
8 months agojanojano
8 months, 3 weeks agoElla008
9 months, 2 weeks agocb4a6c4
9 months, 3 weeks agocertificate988
9 months, 3 weeks ago