A sponsor requires that the established quality standards for the project be met. As a result, the sponsor asks the project manager for stable measures to ensure that the quality is met.
Which three actions should the project manager do? (Choose three.)
victory108
1 day, 6 hours agoea4e1f8
3 months, 1 week ago517f9da
6 months, 1 week agokmsinthesky
6 months, 2 weeks agoAbdelmonm
9 months, 4 weeks ago58e5964
10 months agojanojano
10 months, 3 weeks agoElla008
11 months, 2 weeks agocb4a6c4
11 months, 3 weeks agocertificate988
11 months, 3 weeks ago