Welcome to ExamTopics
ExamTopics Logo
- Expert Verified, Online, Free.
exam questions

Exam PMP All Questions

View all questions & answers for the PMP exam

Exam PMP topic 1 question 956 discussion

Actual exam question from PMI's PMP
Question #: 956
Topic #: 1
[All PMP Questions]

A project has completed the first phase. During the lessons learned meeting, the project manager reported that the project was successful because it was on time, on budget, and on scope. The sponsor objected and said that other project benefits, such as cost reduction of the product and system response time, were not achieved.

What may have caused this situation?

  • A. The change control plan was not followed by the project manager.
  • B. The acceptance criteria were not accurately defined.
  • C. The items did not appear in the project management plan.
  • D. The benefits should have been managed at the organizational level.
Show Suggested Answer Hide Answer
Suggested Answer: B 🗳️

Comments

Chosen Answer:
This is a voting comment (?) , you can switch to a simple comment.
Switch to a voting comment New
certificate988
Highly Voted 11 months, 3 weeks ago
Selected Answer: B
Why D? How system response time etc. need to be defined at organization level. It should be B as acceptance criteria was not defined properly for system response time and cost reduction.
upvoted 5 times
...
victory108
Most Recent 1 day, 5 hours ago
Selected Answer: B
B. The acceptance criteria were not accurately defined
upvoted 1 times
...
UppersquareCapital
6 months ago
Selected Answer: B
Acceptance criteria are essential for defining what success looks like for a project. They should include not only the traditional measures of success such as being on time, on budget, and within scope but also the specific benefits and performance improvements expected by the sponsor and stakeholders, such as cost reduction and system response time improvements. If these criteria were not accurately defined or documented, it can lead to misunderstandings about what constitutes a successful project completion. Properly defined acceptance criteria ensure that there is alignment between the project team and stakeholders (including the sponsor) regarding project outcomes. If these criteria were not clear or comprehensive, the project team might believe they have met their objectives based on scope, time, and budget, while missing critical performance or benefit targets important to the sponsor.
upvoted 1 times
...
517f9da
6 months, 1 week ago
Selected Answer: B
B. The acceptance criteria were not accurately defined. If the acceptance criteria did not accurately include all the project benefits such as cost reduction of the product and system response time, then the project manager would not have managed or measured these aspects. Accurate and comprehensive acceptance criteria ensure that all project benefits are clearly defined and agreed upon, aligning the project's success criteria with the sponsor's expectations.
upvoted 1 times
...
Trytrio
9 months, 3 weeks ago
Selected Answer: B
Acceptance criteria define the specific conditions that must be met for a project to be considered successful. If the acceptance criteria did not include the other project benefits such as cost reduction of the product and system response time, then it's possible that the project team focused solely on meeting the traditional project constraints (time, budget, scope) and did not consider or communicate the broader project objectives and benefits effectively.
upvoted 1 times
...
josephsafiran
10 months ago
Selected Answer: D
Option D suggests that benefits should have been managed at the organizational level, indicating that the project manager may not have adequately addressed or communicated the broader business benefits during the project. Effective benefits realization often requires collaboration between project managers and higher-level organizational management to ensure that project goals align with broader business objectives.
upvoted 1 times
...
UppersquareCapital
10 months, 1 week ago
Selected Answer: D
The situation described suggests that there might be an issue related to the project's overall success criteria and the alignment of project goals with organizational benefits. The most likely cause for this situation is option D. This option indicates that the benefits related to cost reduction and system response time might have been strategic objectives that should have been managed at the organizational level rather than being solely the responsibility of the project manager. If the benefits were not clearly defined, communicated, and managed at the organizational level, there might be a misalignment between the project's success criteria (on time, on budget, on scope) and the broader organizational objectives.
upvoted 2 times
UppersquareCapital
10 months, 1 week ago
While Option B (Acceptance criteria were not accurately defined) could contribute to the issue, Option D addresses the broader context of strategic alignment and benefits management, making it a more comprehensive and likely explanation for the situation described. In well-managed projects, aligning project objectives with organizational goals and ensuring effective benefits management are critical aspects of project success.
upvoted 1 times
...
...
Abdelmonm
10 months, 2 weeks ago
Selected Answer: D
This situation suggests a potential misalignment between the project manager's focus on traditional project constraints (time, budget, and scope) and the sponsor's expectation of broader benefits. It highlights the importance of managing and aligning project benefits not only at the project level but also at the organizational level. Benefits realization should be considered throughout the project lifecycle, and the project manager should work closely with stakeholders to ensure that both project constraints and broader organizational benefits are addressed.
upvoted 1 times
...
mesacgon
10 months, 2 weeks ago
Debe ser B
upvoted 1 times
...
odylec
10 months, 3 weeks ago
Selected Answer: B
B is the answer
upvoted 1 times
...
Ella008
11 months, 2 weeks ago
D: This is an alignment issue. There should have been agreement on acceptance criteria at both organisation and team level.
upvoted 2 times
...
cb4a6c4
11 months, 3 weeks ago
Selected Answer: D
system response time is one of the key issues that has not been addressed which makes answer D the right choice.
upvoted 2 times
...
Community vote distribution
A (35%)
C (25%)
B (20%)
Other
Most Voted
A voting comment increases the vote count for the chosen answer by one.

Upvoting a comment with a selected answer will also increase the vote count towards that answer by one. So if you see a comment that you already agree with, you can upvote it instead of posting a new comment.

SaveCancel
Loading ...