A project has completed the first phase. During the lessons learned meeting, the project manager reported that the project was successful because it was on time, on budget, and on scope. The sponsor objected and said that other project benefits, such as cost reduction of the product and system response time, were not achieved.
What may have caused this situation?
certificate988
Highly Voted 11 months, 3 weeks agovictory108
Most Recent 1 day, 5 hours agoUppersquareCapital
6 months ago517f9da
6 months, 1 week agoTrytrio
9 months, 3 weeks agojosephsafiran
10 months agoUppersquareCapital
10 months, 1 week agoUppersquareCapital
10 months, 1 week agoAbdelmonm
10 months, 2 weeks agomesacgon
10 months, 2 weeks agoodylec
10 months, 3 weeks agoElla008
11 months, 2 weeks agocb4a6c4
11 months, 3 weeks ago