A project manager is using a hybrid approach for a project. The project team created and reviewed the risk log with the stakeholders at the beginning of the project. However, midway through the project, the project team and stakeholders became misaligned with the risks and mitigation strategies.
When should the risks be reviewed to ensure alignment between the project team and the stakeholders?
victory108
3 weeks, 1 day agod370e49
2 months, 1 week agoompk
6 months agosidje
6 months agoAbdelmonm
10 months, 2 weeks agochlaithem
10 months, 2 weeks agoamali999
11 months, 1 week agoJaya12
11 months, 2 weeks agoMaMana
11 months, 2 weeks agoElla008
11 months, 2 weeks agogsap
11 months, 2 weeks agoHanbyul
11 months, 4 weeks ago