A project manager is using a hybrid approach for a project. The project team created and reviewed the risk log with the stakeholders at the beginning of the project. However, midway through the project, the project team and stakeholders became misaligned with the risks and mitigation strategies.
When should the risks be reviewed to ensure alignment between the project team and the stakeholders?
d370e49
1Â week, 1Â day agoompk
3Â months, 4Â weeks agosidje
4Â months agoAbdelmonm
8Â months, 2Â weeks agochlaithem
8Â months, 2Â weeks agoamali999
9Â months agoJaya12
9Â months, 1Â week agoMaMana
9Â months, 1Â week agoElla008
9Â months, 1Â week agogsap
9Â months, 1Â week agoHanbyul
9Â months, 3Â weeks ago